Company logo; a stylized red castle, with the following text below: US Army Corps of Engineers, Walla Walla District
Walla Walla District

Lower Snake River Juvenile Salmon Migration Feasibility Report/Environmental Impact Statement

Appendix D
Natural River Drawdown Engineering




Annex H
Railroad and Roadway Damage Repair Plan


Table H-1 Measurements of Distress from Observations of 1992 Drawdown
Table H-2 Potential Failure Areas Resulting From a Permanent Drawdown
Table H-3 Factors of Safety for Slope Stability
Figure H-1 Railroad and Roadway Repair Small Slope Failures
Figure H-2 Large Slope Failures


Annex H: Railroad and Roadway Damage Repair Plan

H.1 Introduction

This portion of the study addresses of the potential effects of drawdown on railroad and roadway embankments from the Snake River’s confluence with the Columbia River to the Idaho state line. Those effects are settlement and slope stability directly impacted by the drawdown of the reservoir. Problems and anticipated modifications required to resist the erosive forces of the river on the embankments are described in Annex F.

There is no doubt that many of the railroad and highway embankments will be damaged as a result of rapid reservoir drawdown. As drawdown occurs, areas of the embankments along the river are anticipated to fail due to steep slopes, saturated soils, and pore pressure increase. This annex describes the critical elements that contribute to embankment failures from rapid drawdown. It summarizes the observations from the 1992 test drawdown and, from those observations, projects damages resulting from a full reservoir drawdown. It discusses the necessity and impacts of the selected drawdown rate.

H.2 Review of 1992 Drawdown

A test of the reservoir drawdown concept was performed in March 1992, using Lower Granite and Little Goose Dams. The purpose of the test was to gather information regarding the effects of substantially lowering existing reservoirs. The drawdown test was scheduled to be completed within the month of March in order to minimize potential negative impacts to Snake River migrating fish. On March 1 the Lower Granite reservoir was drafted from its starting point of normal minimum operating pool (elevation 223.4 meters [733 feet]) at a rate of 0.6 meters per day for 14 days. Elevation 214.9 meters (705 feet) was achieved on March 15. During subsequent phases. Little Goose reservoir was lowered a total of 3.8 meters and Lower Granite Reservoir was further lowered to elevation 212.4 meters (697 feet) for a total drawdown of 11.0 meters.

During the drawdown the Corps monitored road and railroad embankments along the two reservoirs for potential problems. The following damage on the Lower Granite reservoir was reported:

It was noted that most of the sliding activity associated with the drawdown occurred within slopes consisting of natural deposits of silts, sands, and gravels. For the purposes of this study, stability of natural slopes was not addressed, and efforts focused on man-made embankments. Drawdown of each reservoir of up to 30 meters cannot be assumed to occur without embankment failures.

H.3 Embankment Geometry and Material Considerations

The key to understanding how embankments will behave under drawdown conditions is to understand the embankment materials. Embankments constructed from materials that are so "free-draining" that the soil saturation level falls quickly will have increased stability under drawdown conditions. Stability is decreased if the soil saturation level lags behind the reservoir drawdown level. Therefore the rate of drawdown associated with a minimal lag is related to the "free draining" ability of embankment materials. Greater permeability and porosity of soils results in a greater ability of the material to be "free draining." Although a material may be free draining, the rate of reservoir drawdown may be too fast, resulting in a greater saturation level lag and reduced embankment stability.

The man-made embankments along the lower Snake River are, in general, constructed from locally borrowed materials, and were not subject to the same quality control efforts (grain size and compaction control) which were used in construction of major embankment dams. Also, internal drainage features such as pipes or clean stone drains were not incorporated into the designs. According to railroad and roadway relocation reports and drawings, many embankments were constructed from "random fill" or "granular fill" materials. Compaction was probably used in placing these materials, but it is not clear how much compactive effort was used and what methods were employed. The nature of "random fill" available for borrow in the vicinity of the lower Snake River varies, although the material is predominately sand and gravel with varying amounts of fines (silts and clays passing the No. 200 sieve) and cobbles. The CPRR relocation report (Lower Granite DM 9.2) states that embankment foundations along the relocated alignments consists of bedrock or materials described as relatively clean talus rock, silty talus rock, alluvial material, and wind-deposited sand and silts. Similar materials were used for construction of the relocated road and railroad embankments.

The amount of fines controls the ability of an embankment material to be "free draining," and the amounts of fines in silty talus rock and wind-deposited sands and silts could be significant enough to preclude free draining conditions. Alluvial materials obtained from local terrace gravel deposits and clean talus rock materials likely consist of a predominantly granular mixture of sand, gravel, and cobbles, with a lower percentage of fines than the silty materials. Although aeolian silt often exists on the ground surface of the terrace gravel deposits, it is not likely that significant amounts of fines are present in the alluvial random fill mixtures. The ability of the embankments to be free draining, and therefore more stable during drawdown, depends on the borrow source used to construct the embankments.

Man-made embankments were generally constructed with slopes of 2h:1v, with riprap or rockfill slope protection within the normal reservoir surface operating range. Some embankments, particularly on the Ice Harbor reservoir, have buttress fills against the toe of embankments with slopes of 2.5h:1v to 3h:1v. The embankments along the reservoirs have various top and toe elevations, and the drawdown range will vary from approximately 30 meters just upstream of each dam to nearly no drawdown, or possibly a slight increase in water level, just downstream of each dam. There are many embankment and drawdown rate configurations, and when the variations in embankment geometry, material types and compaction criteria are considered, there are an infinite number of material parameter and geometric combinations.

H.4 Rate of Reservoir Drawdown

The man-made embankments along the four lower Snake River reservoirs were constructed by various entities (including the federal government, state transportation department, and railroad companies) over an extended period of time. Embankment characteristics which vary include the method of embankment construction, embankment geometry, materials used in the embankments, surrounding land topography, embankment foundation materials, and vertical distance of drawdown from the normal reservoir surface elevation. All of these characteristics result in embankments which will behave differently under a drawdown scenario. Behavior may vary from no visible movement or damage to few tension cracks and minor movement or sloughing, to the extreme case of slope failure with extensive movement.

The rate of reservoir drawdown is an important parameter in establishing the schedule for overall embankment dam removal and reservoir drawdown. There are several biological and weather factors which influence the beginning, end, and duration of drawdown. The primary constraint in determining the rate of drawdown is the time period during which the reservoir must be lowered and the embankment removed. Reservoir evacuation cannot begin in any year prior to 1 August. This is because the spring runoff flows extend into June and July and downstream fish migration continues until this time. By January of any year the probability of high flows in the river increases dramatically. These beginning and end point constraints require that the drawdown to be done during this 5-month period. This time is further reduced to allow sufficient time to excavate the embankment and remove cofferdams.

The drawdown rate will be controlled at each dam by the spillway and powerhouse gates. Consequently, a nominal drawdown rate of 0.6 meter (2 feet) per day has been assumed for feasibility level construction planning. While some latitude may be possible as designs and schedules are further developed, the drawdown rate of 0.6 meter per day may only be slightly reduced.

H.5 Methods

The location and extent of embankment failures is extremely difficult to predict based on the uncertainty and variability of materials and methods used in constructing the embankments. However, embankment damage data from the 1992 drawdown of Lower Granite was useful in making such predictions. Table H1 summarizes the specific areas where damage was observed after the 1992 test drawdown. A rational methodology was desired to determine potential damages and subsequent repairs. To estimate the potential for road and railroad embankment failures from observed embankment distress, the study team made the following assumptions:

  1. Drawdown would remove hydrostatic support from saturated materials.

  2. The sections anticipated to undergo settlement are those that are in similar physical positions (height and distance) as the sections that exhibited settlement along the Lower Granite Reservoir during the 1992 drawdown.

  3. The anticipated failure type and characteristics are theoretical and are based on an infinite-slope analysis. Some parameters are based on field observation, and some are based on information resources such as topographic maps and aerial photographs.

 
Table H1
Measurements of Distress From Observations of 1992 Drawdown
Station Station
Location
Feature Description Natural
Slope
(%)
Distance
From
River
(ft)
Height
Above
River
(ft)
Embank
Slope
(%)
Materials
2431+14 Rd. 9000 Pavement Crack 149 ft long, 1 in wide 30 50 30 60 0 ft to 14 ft: silt with scattered rock fragments
2452+26 Rd. 9000 Pavement Crack 58 ft long, ½ in wide 17 50 20 40 0 ft to 15 ft: rock fragments in sandy silt matrix
2457+54 Rd. 9000 Pavement Crack 19 ft long, ¼ in wide 18 50 20 40 0 ft to 15 ft: fine sandy silt with rock fragments
2552+58 Rd. 9000 Pavement Crack 422 ft long, 10 in wide 4 50 20 40 0 ft to 15 ft: fine sandy silt with rock fragments
2605+38 Rd. 9000 Pavement Crack 248 ft long, 1 ft wide 60 30 20 60 0 ft to 15 ft: interbedded silt and sand
2605+38 Rd. 9000 Pavement Crack 63 ft long, ¼ in wide 60 30 20 60 0 ft to 15 ft: interbedded silt and sand
2626+50 Rd. 9000 Pavement Crack 341 ft long, 9 in wide 6 50 20 40 0 ft to 14 ft: silt with scattered rock fragments
2637+06 Rd. 9000 Pavement Crack 154 ft long, 3 in wide 13 20 10 50 0 ft to 15 ft: silt with scattered rock fragments
2684+58 Rd. 9000 Pavement Crack 80 ft long, ¼ in wide 8 50 20 40 0 ft to 14 ft: sandy silt
2710+98 Rd. 9000 Pavement Crack 24 ft long, 6 in wide 27 50 20 40 0 ft to 15 ft: silt with scattered rock fragments
2742+66 Rd. 9000 Pavement Crack 221 ft long, ¾ in wide 50 30 20 65 0 ft to 14 ft: silt with scattered rock fragments
2753+22 Rd. 9000 Pavement Crack 45 ft long, 2 in wide 17 30 20 65 0 ft to 14 ft: rock fragments in silty and ash matrix
2753+22 CPRR Pavement Crack 197 ft long, 15 in wide 17 30 20 65 0 ft to 14 ft: rock fragments in silty and ash matrix
2758+50 CPRR Pavement Crack 33 ft long, 6 in wide 30 30 20 65 0 ft to 14 ft: rock fragments in silty and ash matrix
2758+50 CPRR Pavement Crack 51 ft long, 7 in wide 30 30 20 65 0 ft to 14 ft: rock fragments in silty and ash matrix
2763+78 Rd. 9000/CPRR Pavement Crack 191 ft long, 6 in wide 25 40 20 50 0 ft to 40 ft: interbedded silt and sand
2763+78 Rd. 9000 Pavement Crack 48 ft long, 2 in wide 25 40 20 50 0 ft to 40 ft: interbedded silt and sand
2779+62 Rd. 9000 Pavement Crack 81 ft long, 6 in wide 18 50 20 40 0 ft to 3 ft: sand and gravel, 3 ft+: bedrock
2784+90 Rd. 9000 Pavement Crack 118 ft long, 13 in wide 12 40 20 50 0 ft to 14 ft: rock fragments in silty matrix
2784+90 Rd. 9000 Pavement Crack 102 ft long, 4 in wide 12 40 20 50 0 ft to 14 ft: rock fragments in silty matrix
2784+90 Rd. 9000 Pavement Crack 228 ft long, 13 in wide 12 40 20 50 0 ft to 14 ft: rock fragments in silty matrix
2790+18 Rd. 9000 Pavement Crack 289 ft long, 7 in wide 40 50 20 40 0 ft to 14 ft: rock fragments in silty matrix
2800+74 Rd. 9000 Pavement Crack 313 ft long, 11 in wide 17 50 20 40 0 ft to 14 ft: rock fragments in silty matrix
2806+02 Rd. 9000 Pavement Crack 116 ft long, 9 in wide 40 30 20 65 0 ft to 14 ft: rock fragments in silty matrix
2806+02 Rd. 9000 Pavement Crack 254 ft long, 10 in wide 40 30 20 65 0 ft to 14 ft: rock fragments in silty matrix
2811+30 Rd. 9000 Pavement Crack 241 ft long, 1 in wide 10 50 20 40 0 ft to 14 ft: rock fragments in silty matrix
2816+58 Rd. 9000 Pavement Crack 56 in long, 1/8in wide 20 60 30 50 0 ft to 14 ft: rock fragments in silty matrix
2849+94 Rd. 9000 Pavement Crack 50 ft long, ¼ in wide 30 50 20 40 0 ft to 14 ft: rock fragments in silty matrix
2890+50 Rd. 9000 Pavement Crack 204 ft long, ¼ in wide 26 30 10 30 0 ft to 14 ft: rock fragments
2901+06 Rd. 9000 Pavement Crack 253 ft long, 5 in wide 19 40 15 40 0 ft to 14 ft: rock fragments in silty matrix
2948+58 CPRR Pavement Crack 15 ft long, ¼ in wide 15 40 15 40 3 ft to 6 ft: gravel 6 ft to 12 ft: silt
2953+86 CPRR Pavement Crack 123 ft long, 6 in wide 4 150 20 13 volcanic ash, silt, and sand
2959+14 Rd. 9000 Pavement Crack 30 ft long, 4 in wide 7 50 20/TD> 40 0 ft to 4 ft: talus and colluvium 4 ft+: bedrock
2959+14 Rd. 9000 Pavement Crack 162 ft long, 14 in wide 7 50 20 40 0 ft to 4 ft: talus and colluvium 4 ft+: bedrock
2959+14 Rd. 9000 Pavement Crack 758 ft long, 14 in wide 5 50 20 40 0 ft to 35 ft: interbedded silt and sand
2964+42 Rd. 9000 Pavement Crack 267 ft long, 2 in wide 18 60 20 30 0 ft to 35 ft: interbedded silt and sand

The team developed materials estimates for making repairs to the road and railroad embankments using the following assumptions:

  1. The dimensions for road and railroad cross sections were assumed to be the same as the typical sections used for the road and railroad relocations prior to reservoir establishment. The team also assumed that road and railroad embankments would be constructed with materials meeting current standards.

  2. Material sources were selected from existing sources identified on maps and aerial photographs. All sources were assumed to be available for use and no ownership issues were considered. Haul distances were based on sources shown on maps and aerial photographs.

  3. The embankment repair quantities were assumed to be cumulative for each project.

  4. Since the water level would be far below the structures, the team assumed that riprap would only be needed for shoreline protection in the active water surface zone.

  5. Quantities were based on the following thicknesses:

Combinations of theoretical and practical methods were used to evaluate potential railroad and roadway damage during drawdown. Practical methods were based on observations made during the 1992 Lower Granite Reservoir drawdown. The drawdown test section consisted of Whitman Co. Road No. 9000 and the Camas Prairie Railroad along the Lower Granite Reservoir (Steptoe Canyon to Wawawai Canyon). It appeared that many failures occurred along the contact between the structure fill and the natural foundation material. At other locations, it was evident that the failure extended into the foundation material. Therefore, both modes of failure had to be taken into account. The measurements taken at the time of the observations are summarized in Table H1.

Also, from the observations along the test section, it was evident that nearly all failures occurred at locations that were within 15 meters horizontal distance and 6-meter vertical distance of the reservoir perimeter, and on slopes less than 50 percent (greater than 50 percent would indicate shallow bedrock and greater stability). Therefore, the study team concluded that sections along the river in similar positions with similar physical characteristics would display a similar response. The team also assumed that sections at a horizontal distance of 15 meters to 30 meters and vertical distance greater than 6 meters from the reservoir would display only about 10 percent of the failures of the more closely adjacent sections. The areas of settlement within the test section along the Lower Granite Reservoir are marked on 1 inch = 1,000 feet maps, contract drawing maps, and copies of aerial photographs in the 1992 Reservoir Drawdown Test, Lower Granite and Little Goose Dam (Corps, 1993). Using U.S. Geological Survey, 7.5 minute, 1:24,000 scale quadrangle maps, the study team delineated the sections in both modes of failure types and measured the approximate distance in feet of each.

The study team estimated that a total of 68 potential failure areas could result. These anticipated failure areas are shown in Table H2.

 
Table H-2
Potential Failure Areas Resulting From a Permanent Drawdown
Feature Location Legal
Description
Potential
Failure
Segment
(m)
Class Estimated
Failure
Length
(m)
Mat. So.
No.
Cubic
Meters
Required
Haul
(kilometers)
Ice Harbor Reservoir
BNRR North Bank S18, T9N, R32E 121.9 Low 1.4 1.0 107.8 4.6
BNRR North Bank S18, T9N, R32E 182.9 High 20.6 1.0 1,617.1 3.8
BNRR North Bank S18, T9N, R32E 91.4 Low 1.0 1.0 81.0 3.0
BNRR North Bank S18, T9N, R32E 152.4 High 17.2 1.0 1,349.5 2.4
BNRR North Bank S7, T9N, R32E 304.8 Low 3.4 1.0 269.9 2.3
BNRR North Bank S8, T9N, R32E 487.7 High 55.0 1.0 4,320.0 1.2
BNRR North Bank S4,5, T9N, R32E 1,066.8 Low 12.0 1.0 945.0 1.2
BNRR North Bank S4, T9N, R32E 182.9 High 20.6 1.0 1,620.2 2.3
BNRR North Bank S3, T9N, R32E 335.3 Low 3.4D 1.0 269.9 2.4
BNRR North Bank S34, T10N, R32E 152.4 Low 1.7 1.0 134.6 3.3
BNRR North Bank S26, T10N, R32E 152.4 High 17.2 2.0 1,349.5 1.7
BNRR North Bank S26, T10N, R32E 1,066.8 Low 12.0 2.0 945.0 2.4
BNRR North Bank S23, S26, T10N, R32E 1,317.6 Low 15.5 2.0 1,215.7 0.9
BNRR North Bank S24, T10N, R32E 274.3 Low 3.1 2.0 243.9 0.6
BNRR North Bank S13, T0N, R32E 274.3 High 30.9 3.0 2,429.1 0.3
BNRR North Bank S12, T10N, R32E 792.5 Low 8.9 3.0 701.1 2.1
BNRR North Bank S4, T10N, R33E 701.0 Low 8.9 3.0 701.1 2.1
BNRR North Bank S27,34, T11N, R33E 1,371.6 Low 15.5 3.0 1,215.7 14.6
BNRR North Bank S14,23, T11N, R33E 670.6 Low 7.6 4.0 1,890.1 3.7
Burr Cyn. Rd. North Bank S19, T12N, R34E 121.9 Low 1.4 4.0 107.8 4.6
Burr Cyn. Rd. North Bank S18, T12N, R34E 426.7 High 24.1 4.0 1,890.1 3.7
Burr Cyn. Rd. North Bank S8, 17, T12N, R34E 548.6 High 61.9 4.0 4,858.3 2.4
Wilson Cyn. Rd. North Bank S4, 9, T12N, R34E 2,438.4 High 275.1 4.0 21,596.1 1.2
Gravel Road South Bank S19, T9N, R32E 609.6 High 68.8 13.0 5,398.8 0.6
UPRR South Bank S9, T9N, R32E 1,828.8 Low 20.6 14.0 1,620.2 0.9
UPRR South Bank S3, 4, T9N, R32E 1,828.8 High 206.3 14.0 16,196.5 1.2
UPRR South Bank S2, T9N, R32E 1,676.4 High 189.1 14.0 14,847.0 3.7
UPRR South Bank S36, T10N, R32E 396.2 High 44.7 14.0 3,508.0 4.9
UPRR South Bank S8, T10N, R33E 1,524.0 Low 1.7 15.0 133.8 1.2
UPRR South Bank S34, T11N, R33E 701.0 Low 7.9 15.0 619.3 3.7
UPRR South Bank S26, T11N, R33E 762.0 Low 8.6 16.0 675.1 2.4
UPRR South Bank S24, T11N, R33E 609.6 High 68.8 16.0 5,398.8 0.2
UPRR South Bank S12, T11N, R33E 3,048.0 High 343.8 16.0 26,995.0 2.3
UPRR South Bank S30, 31, T12N, R33E 3,048.0 Low 3.4 19.0 270.7 0.9
UPRR South Bank S17, 19, T12N, R34E 5,181.6 High 402.3 17.0 31,590.2 2.1
UPRR South Bank S8, 9, T12N, R34E 1,219.2 Low 13.7 17.0 1,079.6 0.5
Lower Monumental Reservoir
UPRR South Bank S35, 36, T13N, R34E 1,828.8 High 206.3 18.0 16,201.9 0.8
UPRR South Bank S30, 36, T13N, R34, 35E 1,219.2 High 137.5 20.0 10,793.1 0.9
UPRR South Bank S26, 27, 28, 29, T13N, R35E 7,315.2 High 825.1 21, 22 64,783.8 1.8
UPRR South Bank S21, T13N, R36E 304.8 High 34.4 23.0 2,699.0 1.6
UPRR North Bank S2, 3, T13N, R37E 1,524.0 Low 17.2 5.0 1,349.5 4.0
UPRR North Bank S36, T13N, R374E; S31, T13N, R38E 1,524.0 Low 17.2 5.0 1,349.5 1.2
Hwy 261 South Bank S3, 4, T12N, R37E 609.6 High 68.8 25.0 5,398.8 4.7
Deadman Ck Rd South Bank S32, 33, T13N, R38E 609.6 High 68.8 26.0 5,398.8 1.8
Little Goose Reservoir
CPRR North Bank S22, 23, T13N, R38E   Low 5.2 5a 406.8 2.7
CPRR North Bank S22, 23, T13N, R38E 1,066.8 High 120.4 5a 9,452.7 2.7
CPRR North Bank S24, T13N, R38E 243.8 Low 2.7 5b 215.6 2.4
CPRR North Bank S19, 24, T13N, R38E 1,066.8 High 120.4 5b 9,453.5 0.9
CPRR North Bank S20, 21, T13N, R38E 1,524.0 High 171.9 5b 13,497.5 2.4
CPRR North Bank S22, T13N, R38E 457.2 High 51.8 5b 59,398.7 4.6
CPRR North Bank S7, 11, 14, 23, T13N, R39, 40E 2,590.8 High 756.5 5b 59,399.5 8.5
CPRR North Bank S7, 12, 14, 23, T13N, R39, 40E 1,219.2 Low 1.0 5b 81.0 10.4
CPRR North Bank S13, 14, 22, 23, 27, T14N, R40E 4,876.8 High 550.2 6.0 43,198.4 3.1
CPRR North Bank S13, 17, 18, T14N, R40, 41E 1,524.0 High 171.9 7.0 13,497.5 3.1
CPRR North Bank S15, 16, 17, T14N, R41E 3,962.4 High 446.8 9.0 35,083.7 1.8
CPRR North Bank S20, T14N, R42E 1,219.2 High 137.5 9.0 10,798.4 8.5
CPRR North Bank S20, 21, T14N, R42E 914.4 Low 10.3 9.0 808.9 8.5
CPRR North Bank S13, 14, 23, T14N, R42E 3,048.0 Low 343.8 9.0 26,995.0 15.3
CPRR North Bank S13, 18, 19, T14N, R42E, 43E 1,828.8 High 206.3 10.0 16,197.3 14.6
Hwy 127 South Bank S9, T13N, R40E 1,219.2 High 137.5 27.0 10,797.7 1.2
Deadman Ck Rd South Bank S18, 19, 30, T14N, R43E 1,219.2 Low 13.7 28.0 1,079.6 1.5
Lower Granite Reservoir
CPRR North Bank S33, 34, T14N, R43E S2, T13N, R43E 4,267.2 High 481.3 10.0 37,788.1 9.1
Test Section North Bank Wawawai Creek to Steptoe Creek 16,254.4 High 1,833.4 10 and 11 143,951.2 5.7
BNRR North Bank Steptoe Creek to RM 138.4 16,459.2 Low 185.9 11.0 14,598.5 4.0
Whitman Co. Rd. 9000 North Bank Steptoe Creek to RM 138.4 11,582.4 High 1,306.4 11.0 102,571.9 6.4
Hwy 12 South Bank Alpowa Creek to Red Wolf Bridge 10,972.8 Low 123.7 29 and 30 9,716.5 5.2
Hwy 129 West Bank RM 140.5 to 143 5,486.4 High 618.7 32.0 48,581.9 5.2
Nez Perce Co. Rd. East Bank Hwy 12 to RM 143 5,486.4 Low 62.2 31.0 4,882.0 3.3

The study team also used a theoretical approach to determine the possibility of failure of natural slopes. Using the infinite slope equations for slope stability, the team calculated the factors of safety according to the following parameters:

While holding other parameters constant, the slope and height of the phreatic surface was varied according to the limits expressed above. Slopes range from 10 percent to 50 percent and are shown in radians. The phreatic surface ranges from 0.0 meter to 4.5 meters (anticipated ground surface) above the bedrock surface. The resulting factors of safety are shown in Table H3. The data shown indicate that, at slopes greater than about 30 percent, the factor of safety drops below one when the phreatic surface remains at the ground surface. Typical rates of permeability for silts and sandy silt mixtures (3.5 by 10 -5 m³/s or less) show that the phreatic surface would remain at the ground surface for a reservoir lowering rate of 2 feet per day, creating conditions of slope instability for slopes greater than 30 percent. For slopes of 40 percent and 50 percent, the instability would be much greater.

 
Table H-3
Factors of Safety for Slope Stability
Degree
Slope
Saturated
Material
Thickness
(m)
Factor of
Safety
Degree
Slope
Saturated
Material
Thickness
(m)
Factor of
Safety
Degree
Slope
Saturated
Material
Thickness
(m)
Factor of
Safety
Degree
Slope
Saturated
Material
Thickness
(m)
Factor of
Safety
Degree
Slope
Saturated
Material
Thickness
(m)
Factor of
Safety
5.7 0.0 6.11 11.3 0.0 3.06 16.7 0.0 2.04 21.8 0.0 1.54 26.6 0.0 1.23
5.7 0.3 5.88 11.3 0.3 2.94 16.7 0.3 1.96 21.8 0.3 1.48 26.6 0.3 1.19
5.7 0.6 5.65 11.3 0.6 2.83 16.7 0.6 1.89 21.8 0.6 1.42 26.6 0.6 1.14
5.7 0.9 5.43 11.3 0.9 2.72 16.7 0.9 1.81 21.8 0.9 1.37 26.6 0.9 1.10
5.7 1.2 5.21 11.3 1.2 2.61 16.7 1.2 1.74 21.8 1.2 1.31 26.6 1.2 1.05
5.7 1.5 5.00 11.3 1.5 2.50 16.7 1.5 1.67 21.8 1.5 1.26 26.6 1.5 1.01
5.7 1.8 4.79 11.3 1.8 2.40 16.7 1.8 1.60 21.8 1.8 1.21 26.6 1.8 0.97
5.7 2.1 4.59 11.3 2.1 2.30 16.7 2.1 1.53 21.8 2.1 1.16 26.6 2.1 0.93
5.7 2.4 4.39 11.3 2.4 2.20 16.7 2.4 1.47 21.8 2.4 1.11 26.6 2.4 0.89
5.7 2.7 4.19 11.3 2.7 2.10 16.7 2.7 1.40 21.8 2.7 1.06 26.6 2.7 0.85
5.7 3.0 4.00 11.3 3.0 2.00 16.7 23.0 1.34 21.8 3.0 1.01 26.6 3.0 0.81
5.7 3.4 3.81 11.3 3.4 1.91 16.7 3.4 1.28 21.8 3.4 0.96 26.6 3.4 0.77
5.7 3.7 3.63 11.3 3.7 1.82 16.7 3.7 1.22 21.8 3.7 0.92 26.6 3.7 0.74
5.7 4.0 3.45 11.3 4.0 1.73 16.7 4.0 1.16 21.8 4.0 0.87 26.6 4.0 0.70
5.7 4.3 3.28 11.3 4.3 1.64 16.7 4.3 1.10 21.8 4.3 0.83 26.6 4.3 0.67
5.7 4.6 3.10 11.3 4.6 1.55 16.7 4.6 1.04 21.8 4.6 0.78 26.6 4.6 0.63

The study team devised a typical anticipated small failure from the observed data of the 1992 drawdown and a theoretical model based on natural slope instability. The following parameters were used:

A cross section of the anticipated typical failure is shown in Figure H1. The quantities of construction materials for repair were calculated for the model using typical cross sections developed for the relocation of the County Road 9000 and the Camas Prairie Railroad. The quantities of the repair materials were then calculated for all projected small failures along the Snake River by multiplying the unit quantities (cubic meters per meter) by the number of feet of projected failure (also shown in Figure H1).

  Figure H-1. Railroad and Roadway Repair, Small Slope Failures

Figure H2 shows the cross section of a hypothetical large failure. The failure criteria, dimensions, and associated construction material quantities are also shown in Figure H2. It is anticipated that there would be at least two large failures on both the Little Goose and Lower Granite reservoirs, and one large failure on both the Ice Harbor and Lower Monumental reservoirs.

  Figure H-2. Large Slope Failures

H.6 Conclusions

Drawdown would cause significant damage to road and railroad embankments. Most embankment failures are expected to occur after the reservoirs are significantly drawn down, when the excess weight of the water in the embankment materials would cause a failure. Temporary road detours may be required during and after drawdown to allow vehicle traffic to use roadways. However, railroad embankment failures may result in a shut down of rail traffic until repairs can be made. Rapid response approach to railroad repairs will be critical to minimizing the impacts of interruption of rail service.

H.7 Construction Schedule

Embankment repairs cannot be performed until after drawdown is accomplished. Also, in some areas, it may be necessary to wait several weeks after drawdown to allow the materials to drain and stabilize before repairs can be initiated. The exact number and extent of failures cannot be predicted prior to drawdown. Therefore, multiple equipment rental contracts would be awarded prior to drawdown, allowing repairs to be performed as failures occur. It is anticipated that most damage and consequent repairs would be completed within a few months and up to 1 year after drawdown is complete.


List of Appendixes

Annex A Turbine Passage Modification Plan

Annex B Dam Embankment Excavation Plan

Annex C Temporary Fish Passage Plan

Annex D River Channelization Plan

Annex E Bridge Pier Protection Plan

Annex F Railroad and Highway Embankment Protection Plan

Annex G Drainage Structures Protection Plan

Annex I Lyons Ferry Hatchery Modification Plan

Annex J Habitat Management Units Modification Plan

Annex K Reservoir Revegetation Plan

Annex L Cattle Watering Facilities Management Plan

Annex M Recreation Access Modification Plan

Annex N Cultural Resources Protection Plan

Annex O Irrigation Systems Modification Plan

Annex P Water Well Modification Plan

Annex Q Potlatch Corporation Water Intake Modification Plan

Annex R Other River Structures Modification Plan

Annex S Potlatch Corporation Effluent Diffuser Modification Plan

Annex T PG&E Gas Transmission Main Crossings Modification Plan

Annex U Hydropower Facilities Decommissioning Plan

Annex V Concrete Structures Removal Plan

Annex W Implementation Schedule

Annex X Comprehensive Baseline Cost Estimate


Return to the Main Report