Report text available as:

  • TXT
  • PDF   (PDF provides a complete and accurate display of this text.) Tip ?
 
 
115th Congress                                          Rept. 115-225
                        HOUSE OF REPRESENTATIVES
 1st Session                                                   Part 1

======================================================================



 
            PROMOTING CROSS-BORDER ENERGY INFRASTRUCTURE ACT

                                _______
                                

 July 17, 2017.--Committed to the Committee of the Whole House on the 
              State of the Union and ordered to be printed

                                _______
                                

 Mr. Walden, from the Committee on Energy and Commerce, submitted the 
                               following

                              R E P O R T

                             together with

                            DISSENTING VIEWS

                        [To accompany H.R. 2883]

      [Including cost estimate of the Congressional Budget Office]

    The Committee on Energy and Commerce, to whom was referred 
the bill (H.R. 2883) to establish a more uniform, transparent, 
and modern process to authorize the construction, connection, 
operation, and maintenance of international border-crossing 
facilities for the import and export of oil and natural gas and 
the transmission of electricity, having considered the same, 
report favorably thereon with an amendment and recommend that 
the bill as amended do pass.

                                CONTENTS


Purpose and Summary..............................................     4
Background and Need for Legislation..............................     4
Committee Action.................................................     7
Committee Votes..................................................     7
Oversight Findings and Recommendations...........................    11
New Budget Authority, Entitlement Authority, and Tax Expenditures    11
Congressional Budget Office Estimate.............................    11
Federal Mandates Statement.......................................    12
Statement of General Performance Goals and Objectives............    12
Duplication of Federal Programs..................................    12
Committee Cost Estimate..........................................    12
Earmark, Limited Tax Benefits, and Limited Tariff Benefits.......    12
Disclosure of Directed Rule Makings..............................    12
Advisory Committee Statement.....................................    12
Applicability to Legislative Branch..............................    13
Section-by-Section Analysis of the Legislation...................    13
Changes in Existing Law Made by the Bill, as Reported............    14
Exchange of Letters with Additional Committees of Referral.......    22
Dissenting Views.................................................    27

    The amendment is as follows:
  Strike all after the enacting clause and insert the 
following:

SECTION 1. SHORT TITLE.

  This Act may be cited as the ``Promoting Cross-Border Energy 
Infrastructure Act''.

SEC. 2. APPROVAL FOR BORDER-CROSSING FACILITIES.

  (a) Authorization of Certain Energy Infrastructure Projects at an 
International Boundary of the United States.--
          (1) Authorization.--Except as provided in paragraph (3) and 
        subsection (e), no person may construct, connect, operate, or 
        maintain a border-crossing facility for the import or export of 
        oil or natural gas, or the transmission of electricity, across 
        an international border of the United States without obtaining 
        a certificate of crossing for the border-crossing facility 
        under this subsection.
          (2) Certificate of crossing.--
                  (A) Requirement.--Not later than 120 days after final 
                action is taken, by the relevant official or agency 
                identified under subparagraph (B), under the National 
                Environmental Policy Act of 1969 (42 U.S.C. 4321 et 
                seq.) with respect to a border-crossing facility for 
                which a person requests a certificate of crossing under 
                this subsection, the relevant official or agency, in 
                consultation with appropriate Federal agencies, shall 
                issue a certificate of crossing for the border-crossing 
                facility unless the relevant official or agency finds 
                that the construction, connection, operation, or 
                maintenance of the border-crossing facility is not in 
                the public interest of the United States.
                  (B) Relevant official or agency.--The relevant 
                official or agency referred to in subparagraph (A) is--
                          (i) the Federal Energy Regulatory Commission 
                        with respect to border-crossing facilities 
                        consisting of oil or natural gas pipelines; and
                          (ii) the Secretary of Energy with respect to 
                        border-crossing facilities consisting of 
                        electric transmission facilities.
                  (C) Additional requirement for electric transmission 
                facilities.--In the case of a request for a certificate 
                of crossing for a border-crossing facility consisting 
                of an electric transmission facility, the Secretary of 
                Energy shall require, as a condition of issuing the 
                certificate of crossing under subparagraph (A), that 
                the border-crossing facility be constructed, connected, 
                operated, or maintained consistent with all applicable 
                policies and standards of--
                          (i) the Electric Reliability Organization and 
                        the applicable regional entity; and
                          (ii) any Regional Transmission Organization 
                        or Independent System Operator with operational 
                        or functional control over the border-crossing 
                        facility.
          (3) Exclusions.--This subsection shall not apply to any 
        construction, connection, operation, or maintenance of a 
        border-crossing facility for the import or export of oil or 
        natural gas, or the transmission of electricity--
                  (A) if the border-crossing facility is operating for 
                such import, export, or transmission as of the date of 
                enactment of this Act;
                  (B) if a permit described in subsection (d) for the 
                construction, connection, operation, or maintenance has 
                been issued; or
                  (C) if an application for a permit described in 
                subsection (d) for the construction, connection, 
                operation, or maintenance is pending on the date of 
                enactment of this Act, until the earlier of--
                          (i) the date on which such application is 
                        denied; or
                          (ii) two years after the date of enactment of 
                        this Act, if such a permit has not been issued 
                        by such date.
          (4) Effect of other laws.--
                  (A) Application to projects.--Nothing in this 
                subsection or subsection (e) shall affect the 
                application of any other Federal statute to a project 
                for which a certificate of crossing for a border-
                crossing facility is requested under this subsection.
                  (B) Natural gas act.--Nothing in this subsection or 
                subsection (e) shall affect the requirement to obtain 
                approval or authorization under sections 3 and 7 of the 
                Natural Gas Act for the siting, construction, or 
                operation of any facility to import or export natural 
                gas.
                  (C) Oil pipelines.--Nothing in this subsection or 
                subsection (e) shall affect the authority of the 
                Federal Energy Regulatory Commission with respect to 
                oil pipelines under section 60502 of title 49, United 
                States Code.
  (b) Importation or Exportation of Natural Gas to Canada and Mexico.--
Section 3(c) of the Natural Gas Act (15 U.S.C. 717b(c)) is amended by 
adding at the end the following: ``In the case of an application for 
the importation of natural gas from, or the exportation of natural gas 
to, Canada or Mexico, the Commission shall grant the application not 
later than 30 days after the date on which the Commission receives the 
complete application.''.
  (c) Transmission of Electric Energy to Canada and Mexico.--
          (1) Repeal of requirement to secure order.--Section 202(e) of 
        the Federal Power Act (16 U.S.C. 824a(e)) is repealed.
          (2) Conforming amendments.--
                  (A) State regulations.--Section 202(f) of the Federal 
                Power Act (16 U.S.C. 824a(f)) is amended by striking 
                ``insofar as such State regulation does not conflict 
                with the exercise of the Commission's powers under or 
                relating to subsection 202(e)''.
                  (B) Seasonal diversity electricity exchange.--Section 
                602(b) of the Public Utility Regulatory Policies Act of 
                1978 (16 U.S.C. 824a-4(b)) is amended by striking ``the 
                Commission has conducted hearings and made the findings 
                required under section 202(e) of the Federal Power 
                Act'' and all that follows through the period at the 
                end and inserting ``the Secretary has conducted 
                hearings and finds that the proposed transmission 
                facilities would not impair the sufficiency of electric 
                supply within the United States or would not impede or 
                tend to impede the coordination in the public interest 
                of facilities subject to the jurisdiction of the 
                Secretary.''.
  (d) No Presidential Permit Required.--No Presidential permit (or 
similar permit) required under Executive Order No. 13337 (3 U.S.C. 301 
note), Executive Order No. 11423 (3 U.S.C. 301 note), section 301 of 
title 3, United States Code, Executive Order No. 12038, Executive Order 
No. 10485, or any other Executive order shall be necessary for the 
construction, connection, operation, or maintenance of an oil or 
natural gas pipeline or electric transmission facility, or any border-
crossing facility thereof.
  (e) Modifications to Existing Projects.--No certificate of crossing 
under subsection (a), or permit described in subsection (d), shall be 
required for a modification to--
          (1) an oil or natural gas pipeline or electric transmission 
        facility that is operating for the import or export of oil or 
        natural gas or the transmission of electricity as of the date 
        of enactment of this Act;
          (2) an oil or natural gas pipeline or electric transmission 
        facility for which a permit described in subsection (d) has 
        been issued; or
          (3) a border-crossing facility for which a certificate of 
        crossing has previously been issued under subsection (a).
  (f) Effective Date; Rulemaking Deadlines.--
          (1) Effective date.--Subsections (a) through (e), and the 
        amendments made by such subsections, shall take effect on the 
        date that is 1 year after the date of enactment of this Act.
          (2) Rulemaking deadlines.--Each relevant official or agency 
        described in subsection (a)(2)(B) shall--
                  (A) not later than 180 days after the date of 
                enactment of this Act, publish in the Federal Register 
                notice of a proposed rulemaking to carry out the 
                applicable requirements of subsection (a); and
                  (B) not later than 1 year after the date of enactment 
                of this Act, publish in the Federal Register a final 
                rule to carry out the applicable requirements of 
                subsection (a).
  (g) Definitions.--In this section--
          (1) the term ``border-crossing facility'' means the portion 
        of an oil or natural gas pipeline or electric transmission 
        facility that is located at an international boundary of the 
        United States;
          (2) the term ``modification'' includes a reversal of flow 
        direction, change in ownership, change in flow volume, addition 
        or removal of an interconnection, or an adjustment to maintain 
        flow (such as a reduction or increase in the number of pump or 
        compressor stations);
          (3) the term ``natural gas'' has the meaning given that term 
        in section 2 of the Natural Gas Act (15 U.S.C. 717a);
          (4) the term ``oil'' means petroleum or a petroleum product;
          (5) the terms ``Electric Reliability Organization'' and 
        ``regional entity'' have the meanings given those terms in 
        section 215 of the Federal Power Act (16 U.S.C. 824o); and
          (6) the terms ``Independent System Operator'' and ``Regional 
        Transmission Organization'' have the meanings given those terms 
        in section 3 of the Federal Power Act (16 U.S.C. 796).

                          Purpose and Summary

    H.R. 2883, the ``Promoting Cross-Border Energy 
Infrastructure Act,'' was introduced by Rep. Mullin (R-OK) and 
Rep. Gene Green (D-TX) on June 12, 2017. H.R. 2883 would 
establish coordinated procedures to authorize the construction, 
connection, operation, and maintenance of international border-
crossing facilities for the import and export of oil and 
natural gas and the transmission of electricity. The 
legislation would replace the requirements established under 
Executive Order that persons obtain a Presidential Permit 
before constructing an oil and gas pipeline or electric 
transmission facility that crosses the U.S. border between 
Canada or Mexico.

                  Background and Need for Legislation

    Trade of oil, gas, and electricity among the United States, 
Canada, and Mexico has resulted in one large, integrated North 
American market. According to the Congressional Research 
Service (CRS), the value of energy trade between the United 
States and its North American neighbors exceeded $140 billion 
in 2015, with $100 billion in U.S. energy imports and over $40 
billion in exports.\1\ The expansion of cross-border energy 
transportation infrastructure--pipelines for oil and natural 
gas and transmission lines for electricity--is necessary to 
enable increased energy trade. A number of new projects are 
currently under construction or proposed to further expand 
cross-border capacity, but they face considerable Federal 
regulatory uncertainty.
---------------------------------------------------------------------------
    \1\Congressional Research Service. Cross-Border Energy Trade in 
North America: Present and Potential. January 30, 2017.
---------------------------------------------------------------------------
    Congress has not asserted its authority to establish 
procedures for permitting cross-border energy infrastructure. 
In the absence of a statutorily directed process, agencies have 
made decisions regarding cross-border energy infrastructure 
within the context of their interpretation of a series of 
Executive Orders dating back to the 1950's. Under these Orders, 
the Secretary of State has the authority to issue Presidential 
permits for cross-border liquids pipelines, the Federal Energy 
Regulatory Commission (FERC) for cross-border natural gas 
pipelines, and the Department of Energy (DOE) for cross-border 
electric transmission facilities.\2\
---------------------------------------------------------------------------
    \2\The State Department makes permitting decisions based on 
directives in Executive Order 11423 (E.O.), as amended by E.O. 13337. 
FERC and DOE make permitting decisions in accordance with E.O. 10485, 
as amended by E.O. 12038.
---------------------------------------------------------------------------

Cross-border electric transmission facilities

    The U.S. currently has over 40 cross-border electric 
transmission lines between the U.S. and Canada and the U.S. and 
Mexico. These interconnections--the majority of which are 
located at the Canadian border--have improved reliability, fuel 
diversity, and efficiencies in system operations, particularly 
for the New England and Midwest regions. Over the last decade, 
the U.S. has experienced a marked trend of growing net 
electricity imports from both Canada and Mexico, although 
Canada is by far the greater trading partner. Future cross-
border electricity trade will be a function of both the 
development of future generation capacity and the availability 
of cross-border transmission infrastructure to move electric 
power. Under current law, applications for new transmission 
projects will be required to obtain a Presidential Permit and 
an export authorization from the Secretary of Energy. There are 
currently four pending export authorization applications and 
eight pending Presidential Permit applications before DOE.\3\
---------------------------------------------------------------------------
    \3\DOE, Office of Electricity Delivery and Energy Reliability, 
``Pending Applications.''
---------------------------------------------------------------------------

Cross-border natural gas pipelines

    There are over 50 operating cross-border natural gas 
pipelines between the U.S. and Canada and the U.S. and 
Mexico.\4\ Over the last five years, natural gas pipeline 
capacity between the U.S. and Mexico has grown significantly, 
and it is projected to double through 2018, based on four new 
projects currently under construction and two in the planning 
stage.\5\
---------------------------------------------------------------------------
    \4\CRS Memorandum, ``Presidential Permitting of Border Crossing 
Energy Facilities,'' at Table 1 (Aug. 16, 2013).
    \5\U.S. Energy Information Administration, ``New U.S. Border-
Crossing Pipelines Bring Shale Gas to More Regions in Mexico,'' 
December 1, 2016.
---------------------------------------------------------------------------
    Under the current process to construct and operate a cross-
border natural gas pipeline, any person seeking to construct 
and operate such facilities must obtain two separate 
authorizations from FERC for the facility and an authorization 
from DOE to import or export natural gas. FERC authorization 
under section 3 of the NGA is necessary for siting, 
construction, or operation of facilities to import or export 
natural gas. In addition, pursuant to Executive Order 10485 
(September 3, 1954), as amended by Executive Order 12038 
(February 3, 1978), a Presidential Permit also must be obtained 
for the cross-border portion of the pipeline. Any person 
seeking to import or export natural gas must also obtain a 
separate authorization from DOE under section 3 of the NGA.\6\ 
For imports and exports to countries with which the U.S. has a 
Free Trade Agreement, such as Canada and Mexico, DOE is 
required to grant requests ``without modification or delay.''
---------------------------------------------------------------------------
    \6\15 USC Sec. 717b.
---------------------------------------------------------------------------
    Executive Order 12038 provides that, before a Presidential 
Permit is issued, there must be a finding that the action is 
consistent with the public interest. The criteria used for 
determining if an application is consistent with the public 
interest is identical to the criteria for approving 
applications for the siting, construction, and operation of 
import and export facilities under section 3 of the NGA.
    For ``border facilities'' subject to Presidential Permit 
and NGA section 3 review, discretion is given to FERC on a 
project-by-project basis to determine the exact scope of the 
project review, and therefore the exact parameters of the 
Presidential Permit and section 3 application. FERC looks for a 
physical feature on a project, such as a valve or meter on the 
interior side of the U.S. border, as an endpoint for what may 
be considered to lie within the Commission's jurisdiction and 
therefore subject to its review procedures. From the physical 
feature, the border crossing facilities would be construed to 
extend to either the U.S./Canada or U.S./Mexico border.

Cross-border oil pipelines

    The U.S. currently has 20 operating cross-border oil 
pipelines between the U.S. and Canada and the U.S. and Mexico. 
Pipelines dominate crude movements between Canada and the U.S., 
while no crude oil pipeline capacity currently exists or is 
proposed between the U.S. and Mexico. There are currently three 
pending applications for Presidential Permits for either new or 
existing cross-border oil pipelines between the U.S. and 
Canada.\7\
---------------------------------------------------------------------------
    \7\Department of State, Bureau of Energy Resources ``Pending 
Applications.''
---------------------------------------------------------------------------
    Under the current process to construct and operate an 
international cross-border oil pipeline, any person seeking to 
construct and operate such facilities must obtain a 
Presidential Permit pursuant to Executive Order 13337 from the 
Department of State. Under Executive Order 13337, the Secretary 
of State is to approve cross-border oil pipelines that have 
been determined to ``serve the national interest.'' Although 
the Department of State will not necessarily evaluate the same 
factors for each application for a Presidential Permit, its 
evaluation considers such things as the environmental impacts 
of the proposed project (associated closely with compliance 
with NEPA), stability of trading partners from whom the U.S. 
obtains crude oil, and the security of transport pathways for 
crude oil supplies to the U.S., and the economic benefits to 
the U.S.

Need for statutory authority for cross-border permitting

    The Committee finds that cross-border permitting authority 
should be explicitly granted by statute, as opposed to the 
current framework created entirely by the Executive Branch. The 
Committee is concerned by the inconsistent, ad hoc manner in 
which Presidential Permit authority has been exercised among 
the agencies to which it has been delegated by Executive Order. 
This issue came into particular focus in the context of the 
State Department's review of the Keystone XL pipeline proposal, 
which originally applied for a Presidential Permit in 2008 and 
did not receive approval until 2017.
    The Committee finds that the statutorily directed process 
for cross-border permitting embodied by H.R. 2883 would lead to 
more objective and timely decisions, which in turn would create 
jobs, strengthen our nation's energy security, and support 
affordable and reliable energy for Americans.
    H.R. 2883 would replace the Presidential Permit requirement 
with a more transparent, efficient, and effective review 
process. The legislation would require persons seeking to 
construct, connect, operate, or maintain a border-crossing 
facility for the import or export of oil or natural gas, or the 
transmission of electricity, to obtain a Certificate of 
Crossing. The term ``border-crossing facility,'' and thus what 
may be considered jurisdictional for the purposes of the 
Certificate of Crossing review, means the portion of the 
pipeline or transmission facility that is located at an 
international boundary. This description is consistent with 
FERC's established procedures for review of Presidential Permit 
and NGA section 3 applications. Under the legislation, the 
relevant official would issue the certificate of crossing 
unless it is found that the construction, connection, 
operation, or maintenance of border facilities comprising the 
cross-border segment is not in the public interest of the 
United States. Consistent with FERC's existing procedures for 
review of cross-border gas pipelines, the cross-border segment 
of the border crossing facility would be identified as the 
segment spanning from the international boundary to a physical 
feature within close proximity, such as a valve or meter. The 
legislation would have no effect on the requirement to obtain 
approval or authorization under sections 3 and 7 of the NGA or 
the authorities of FERC with respect to the siting of oil 
pipelines upstream or downstream of a border crossing facility. 
The legislation would also have no effect on any other Federal 
statute that would apply to a project for which a Certificate 
of Crossing is required, including any requirements of the 
National Environmental Policy Act.

                            Committee Action

    On May 3, 2017, the Subcommittee on Energy held a hearing 
on discussion draft entitled ``Promoting Cross-Border Energy 
Infrastructure Act.'' The Subcommittee received testimony from:
           Terry Turpin, Director, Office of Energy 
        Projects, Federal Energy Regulatory Commission;
           John Katz, Deputy Associate General Counsel, 
        Office of the General Counsel, Federal Energy 
        Regulatory Commission;
           Jeffrey Leahey, Deputy Executive Director, 
        National Hydropower Association;
           Donald Santa, President and CEO, Interstate 
        Natural Gas Association of America;
           Andy Black, President and CEO, Association 
        of Oil Pipe Lines;
           Jeffrey Soth, Legislative and Political 
        Director, International Union of Operating Engineers;
           Bob Irvin, President and CEO, American 
        Rivers; and,
           Jennifer Danis, Senior Staff Attorney, 
        Eastern Environmental Law Center.
    On June 22, 2017, the Subcommittee on Energy met in open 
markup session and forwarded H.R. 2883, without amendment, to 
the full Committee by a record vote of 18 yeas and 12 nays. On 
June 28, 2017, the full Committee on Energy and Commerce met in 
open markup session and ordered H.R. 2883, as amended, 
favorably reported to the House by a record vote of 31 yeas and 
20 nays.

                            Committee Votes

    Clause 3(b) of rule XIII requires the Committee to list the 
record votes on the motion to report legislation and amendments 
thereto. The following reflects the record votes taken during 
the Committee consideration:

[GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT]

                 Oversight Findings and Recommendations

    Pursuant to clause 2(b)(1) of rule X and clause 3(c)(1) of 
rule XIII, the Committee held a hearing and made findings that 
are reflected in this report.

   New Budget Authority, Entitlement Authority, and Tax Expenditures

    Pursuant to clause 3(c)(2) of rule XIII, the Committee 
finds that H.R. 2883 would result in no new or increased budget 
authority, entitlement authority, or tax expenditures or 
revenues.

                  Congressional Budget Office Estimate

    Pursuant to clause 3(c)(3) of rule XIII, the following is 
the cost estimate provided by the Congressional Budget Office 
pursuant to section 402 of the Congressional Budget Act of 
1974:

                                     U.S. Congress,
                               Congressional Budget Office,
                                     Washington, DC, July 14, 2017.
Hon. Greg Walden,
Chairman, Committee on Energy and Commerce,
House of Representatives, Washington, DC.
    Dear Mr. Chairman: The Congressional Budget Office has 
prepared the enclosed cost estimate for H.R. 2883, the 
Promoting Cross-Border Energy Infrastructure Act.
    If you wish further details on this estimate, we will be 
pleased to provide them. The CBO staff contact is Megan 
Carroll.
            Sincerely,
                                             Mark P. Hadley
                                        (For Keith Hall, Director).
    Enclosure.

H.R. 2883--Promoting Cross-Border Energy Infrastructure Act

    H.R. 2883 would make changes to permitting requirements for 
oil and natural gas pipelines and electric transmission 
facilities that cross international borders. In particular, the 
bill would eliminate the existing requirement that sponsors of 
such infrastructure obtain a Presidential permit. Instead, H.R. 
2883 would require those sponsors to obtain a certificate of 
crossing. Under the bill, the Federal Energy Regulatory 
Commission (FERC) would issue those certificates for oil and 
natural gas pipelines; the Secretary of Energy would issue them 
for electric transmission facilities. The change in permitting 
requirements would apply to new projects and modifications of 
certain existing projects as specified by the bill.
    CBO estimates that implementing H.R. 2883 would have no 
significant net effect on the federal budget. Relative to 
current law, we expect that any changes to administrative costs 
incurred by the Department of Energy would not exceed $500,000 
in any year; such spending would be subject to the availability 
of appropriated funds. Further, because FERC recovers 100 
percent of its costs through user fees, any change in that 
agency's costs (which are controlled through annual 
appropriation acts) would be offset by an equal change in fees 
that the commission charges, resulting in no net change in 
federal spending.
    Enacting H.R. 2883 would not affect direct spending or 
revenues; therefore, pay-as-you-go procedures do not apply. CBO 
estimates that enacting H.R. 2883 would not increase net direct 
spending or on-budget deficits in any of the four consecutive 
10-year periods beginning in 2028.
    H.R. 2883 contains no intergovernmental or private-sector 
mandates as defined in the Unfunded Mandate Reform Act and 
would impose no costs on state, local, or tribal governments.
    The CBO staff contact for this estimate is Megan Carroll. 
The estimate was approved by H. Samuel Papenfuss, Deputy 
Assistant Director for Budget Analysis.

                       Federal Mandates Statement

    The Committee adopts as its own the estimate of Federal 
mandates prepared by the Director of the Congressional Budget 
Office pursuant to section 423 of the Unfunded Mandates Reform 
Act.

         Statement of General Performance Goals and Objectives

    Pursuant to clause 3(c)(4) of rule XIII, the general 
performance goal or objective of this legislation is to 
establish coordinated procedures to authorize the construction, 
connection, operation, and maintenance of international border-
crossing facilities for the import and export of oil and 
natural gas and the transmission of electricity.

                    Duplication of Federal Programs

    Pursuant to clause 3(c)(5) of rule XIII, no provision of 
H.R. 2883 is known to be duplicative of another Federal 
program, including any program that was included in a report to 
Congress pursuant to section 21 of Public Law 111-139 or the 
most recent Catalog of Federal Domestic Assistance.

                        Committee Cost Estimate

    Pursuant to clause 3(d)(1) of rule XIII, the Committee 
adopts as its own the cost estimate prepared by the Director of 
the Congressional Budget Office pursuant to section 402 of the 
Congressional Budget Act of 1974.

       Earmark, Limited Tax Benefits, and Limited Tariff Benefits

    Pursuant to clause 9(e), 9(f), and 9(g) of rule XXI, the 
Committee finds that H.R. 2883 contains no earmarks, limited 
tax benefits, or limited tariff benefits.

                  Disclosure of Directed Rule Makings

    Pursuant to section 3(i) of H. Res. 5, the Committee finds 
that H.R. 2883 contains no directed rule makings.

                      Advisory Committee Statement

    No advisory committees within the meaning of section 5(b) 
of the Federal Advisory Committee Act were created by this 
legislation.

                  Applicability to Legislative Branch

    The Committee finds that the legislation does not relate to 
the terms and conditions of employment or access to public 
services or accommodations within the meaning of section 
102(b)(3) of the Congressional Accountability Act.

             Section-by-Section Analysis of the Legislation


Section 1. Short title

    This section provides the short title of ``Promoting Cross-
Border Energy Infrastructure Act.''

Section 2. Approval for border-crossing facilities

    Section 2(a)(1) provides that no person may construct, 
connect, operate, or maintain a border-crossing facility for 
the import or export of oil or natural gas, or the transmission 
of electricity, across an international border of the United 
States without obtaining a certificate of crossing.
    Section 2(a)(2) instructs relevant officials or agencies, 
in consultation with appropriate Federal agencies, to issue a 
certificate of crossing for a border-crossing facility within 
120 days after final action is taken, unless the relevant 
official or agency finds that the construction, connection, 
operation, or maintenance of the border-crossing facility is 
not in the public interest of the United States. The relevant 
official or agency with respect to border-crossing facilities 
consisting of oil or natural gas pipelines is the Federal 
Energy Regulatory Commission. The relevant official or agency 
with respect to electric transmission facilities is the 
Secretary of Energy. This section also provides additional 
requirements for electric transmission facilities.
    Section 2(a)(3) instructs that subsection (a) shall not 
apply to border-crossing facilities that are in operation on 
the date of enactment of this Act if a permit as described in 
subsection (d) has been issued, or if a permit as described in 
subsection (d) is pending and meets certain requirements.
    Section 2(a)(4) specifies that nothing in subsection (a) or 
subsection (e) shall affect the application of any other 
Federal statute to a project for which a certificate of 
crossing for a border-crossing facility is requested; the 
requirement to obtain approval or authorization under sections 
3 and 7 of the NGA or the authority of the FERC with respect to 
oil pipelines under section 60502 of title 49, United States 
Code.
    Section 2(b) amends section 3(c) of the NGA directing FERC 
to grant an application for the importation of natural gas 
from, or exportation of natural gas to, Canada and Mexico not 
later than 30 days after the date on which the Commission 
receives the complete application.
    Section 2(c) repeals section 202(e) of the Federal Power 
Act, eliminating the requirement to secure an order from FERC 
to transmit electric energy from the United States to a foreign 
country. This section also contains conforming amendments 
related to State regulations and seasonal diversity electricity 
exchange.
    Section 2(d) specifies that no Presidential Permit or any 
other Executive Order shall be necessary for the construction, 
connection, operation, or maintenance of an oil or natural gas 
pipeline or electric transmission facility, or any border-
crossing facility.
    Section 2(e) directs that no certificate of crossing under 
subsection (a) or permit described in subsection (d) shall be 
required for a modification to an oil or natural gas pipeline 
or electric transmission facility that is operating for the 
import or export of energy as of the date of enactment of this 
Act. Additionally, a certificate of crossing or a permit shall 
not be required for a modification to an oil or natural gas 
pipeline or electric transmission facility for which a permit 
described in subsection (d) has been issued, or for which a 
certificate of crossing has previously been issued under 
subsection (a).
    Section 2(f) specifies that subsections (a) through (c) 
shall take effect on the date that is one year after the date 
of enactment of this Act. Each relevant official or agency 
shall publish in the Federal Register a notice of a proposed 
rulemaking to carry out the requirements of subsection (a) 
within 180 days after the date of enactment of this Act. Not 
later than one year after the date of enactment, the relevant 
officials or agencies shall publish a final rule in the Federal 
Register.
    Section 2(g) provides definitions for terms used throughout 
this section.

         Changes in Existing Law Made by the Bill, as Reported

  In compliance with clause 3(e) of rule XIII of the Rules of 
the House of Representatives, changes in existing law made by 
the bill, as reported, are shown as follows (existing law 
proposed to be omitted is enclosed in black brackets, new 
matter is printed in italics, and existing law in which no 
change is proposed is shown in roman):

NATURAL GAS ACT

           *       *       *       *       *       *       *



        exportation or importation of natural gas; lng terminals

  Sec. 3. (a) After six months from the date on which this act 
takes effect no person shall export any natural gas from the 
United States to a foreign country or import any natural gas 
from a foreign country without first having secured an order of 
the Commission authorizing it to do so. The Commission shall 
issue such order upon application, unless, after opportunity 
for hearing, it finds that the proposed exportation or 
importation will not be consistent with the public interest. 
The Commission may by its order grant such application, in 
whole or in part, with such modification and upon such terms 
and conditions as the Commission may find necessary or 
appropriate, and may from time to time, after opportunity for 
hearing, and for good cause shown, make such supplemental order 
in the premises as it may find necessary or appropriate.
  (b) With respect to natural gas which is imported into the 
United States from a nation with which there is in effect a 
free trade agreement requiring national treatment for trade in 
natural gas, and with respect to liquefied natural gas--
          (1) the importation of such natural gas shall be 
        treated as a ``first sale'' within the meaning of 
        section 2(21) of the Natural Gas Policy Act of 1978; 
        and
          (2) the Commission shall not, on the basis of 
        national origin, treat any such imported natural gas on 
        an unjust, unreasonable, unduly discriminatory, or 
        preferential basis.
  (c) For purposes of subsection (a), the importation of the 
natural gas referred to in subsection (b), or the exportation 
of natural gas to a nation with which there is in effect a free 
trade agreement requiring national treatment for trade in 
natural gas, shall be deemed to be consistent with the public 
interest, and applications for such importation or exportation 
shall be granted without modification or delay. In the case of 
an application for the importation of natural gas from, or the 
exportation of natural gas to, Canada or Mexico, the Commission 
shall grant the application not later than 30 days after the 
date on which the Commission receives the complete application.
  (d) Except as specifically provided in this Act, nothing in 
this Act affects the rights of States under--
          (1) the Coastal Zone Management Act of 1972 (16 
        U.S.C. 1451 et seq.);
          (2) the Clean Air Act (42 U.S.C. 7401 et seq.); or
          (3) the Federal Water Pollution Control Act (33 
        U.S.C. 1251 et seq.).
  (e)(1) The Commission shall have the exclusive authority to 
approve or deny an application for the siting, construction, 
expansion, or operation of an LNG terminal. Except as 
specifically provided in this Act, nothing in this Act is 
intended to affect otherwise applicable law related to any 
Federal agency's authorities or responsibilities related to LNG 
terminals.
  (2) Upon the filing of any application to site, construct, 
expand, or operate an LNG terminal, the Commission shall--
          (A) set the matter for hearing;
          (B) give reasonable notice of the hearing to all 
        interested persons, including the State commission of 
        the State in which the LNG terminal is located and, if 
        not the same, the Governor-appointed State agency 
        described in section 3A;
          (C) decide the matter in accordance with this 
        subsection; and
          (D) issue or deny the appropriate order accordingly.
  (3)(A) Except as provided in subparagraph (B), the Commission 
may approve an application described in paragraph (2), in whole 
or part, with such modifications and upon such terms and 
conditions as the Commission find necessary or appropriate.
  (B) Before January 1, 2015, the Commission shall not--
          (i) deny an application solely on the basis that the 
        applicant proposes to use the LNG terminal exclusively 
        or partially for gas that the applicant or an affiliate 
        of the applicant will supply to the facility; or
          (ii) condition an order on--
                  (I) a requirement that the LNG terminal offer 
                service to customers other than the applicant, 
                or any affiliate of the applicant, securing the 
                order;
                  (II) any regulation of the rates, charges, 
                terms, or conditions of service of the LNG 
                terminal; or
                  (III) a requirement to file with the 
                Commission schedules or contracts related to 
                the rates, charges, terms, or conditions of 
                service of the LNG terminal.
  (C) Subparagraph (B) shall cease to have effect on January 1, 
2030.
  (4) An order issued for an LNG terminal that also offers 
service to customers on an open access basis shall not result 
in subsidization of expansion capacity by existing customers, 
degradation of service to existing customers, or undue 
discrimination against existing customers as to their terms or 
conditions of service at the facility, as all of those terms 
are defined by the Commission.
  (f)(1) In this subsection, the term ``military 
installation''--
          (A) means a base, camp, post, range, station, yard, 
        center, or homeport facility for any ship or other 
        activity under the jurisdiction of the Department of 
        Defense, including any leased facility, that is located 
        within a State, the District of Columbia, or any 
        territory of the United States; and
          (B) does not include any facility used primarily for 
        civil works, rivers and harbors projects, or flood 
        control projects, as determined by the Secretary of 
        Defense.
  (2) The Commission shall enter into a memorandum of 
understanding with the Secretary of Defense for the purpose of 
ensuring that the Commission coordinate and consult with the 
Secretary of Defense on the siting, construction, expansion, or 
operation of liquefied natural gas facilities that may affect 
an active military installation.
  (3) The Commission shall obtain the concurrence of the 
Secretary of Defense before authorizing the siting, 
construction, expansion, or operation of liquefied natural gas 
facilities affecting the training or activities of an active 
military installation.

           *       *       *       *       *       *       *

                              ----------                              


FEDERAL POWER ACT

           *       *       *       *       *       *       *



PART II--REGULATION OF ELECTRIC UTILITY COMPANIES ENGAGED IN INTERSTATE 
COMMERCE

           *       *       *       *       *       *       *



     interconnection and coordination of facilities; emergencies; 
                   transmission to foreign countries

  Sec. 202. (a) For the purpose of assuring an abundant supply 
of electric energy throughout the United States with the 
greatest possible economy and with regard to the proper 
utilization and conservation of natural resources, the 
Commission is empowered and directed to divide the country into 
regional districts for the voluntary interconnection and 
coordination of facilities for the generation, transmission, 
and sale of electric energy, and it may at any time thereafter, 
upon its own motion or upon application, make such 
modifications thereof as in its judgment will promote the 
public interest. Each such district shall embrace an area 
which, in the judgment of the Commission, can economically be 
served by such interconnected and coordinated electric 
facilities. It shall be the duty of the Commission to promote 
and encourage such interconnection and coordination within each 
such district and between such districts. Before establishing 
any such district and fixing or modifying the boundaries 
thereof the Commission shall give notice to the State 
commission of each State situated wholly or in part within such 
district, and shall afford each such State commission 
reasonable opportunity to present its views and 
recommendations, and shall receive and consider such views and 
recommendations.
  (b) Whenever the Commission, upon application of any State 
commission or of any person engaged in the transmission or sale 
of electric energy, and after notice to each State commission 
and public utility affected and after opportunity for hearing, 
finds such action necessary or appropriate in the public 
interest it may by order direct a public utility (if the 
Commission finds that no undue burden will be placed upon such 
public utility thereby) to establish physical connection of its 
transmission facilities with the facilities of one or more 
other persons engaged in the transmission or sale of electric 
energy, to sell energy to or exchange energy with such persons: 
Provided, That the Commission shall have no authority to compel 
the enlargement of generating facilities for such purposes, nor 
to compel such public utility to sell or exchange energy when 
to do so would impair its ability to render adequate service to 
its customers. The Commission may prescribe the terms and 
conditions of the arrangement to be made between the persons 
affected by any such order, including the apportionment of cost 
between them and the compensation or reimbursement reasonably 
due to any of them.
  (c)(1) During the continuance of any war in which the United 
States is engaged, or whenever the Commission determines that 
an emergency exists by reason of a sudden increase in the 
demand for electric energy, or a shortage of electric energy or 
of facilities for the generation or transmission of electric 
energy, or of fuel or water for generating facilities, or other 
causes, the Commission shall have authority, either upon its 
own motion or upon complaint, with or without notice, hearing, 
or report, to require by order such temporary connections of 
facilities and such generation, delivery, interchange, or 
transmission of electric energy as in its judgment will best 
meet the emergency and serve the public interest. If the 
parties affected by such order fail to agree upon the terms of 
any arrangement between them in carrying out such order, the 
Commission, after hearing held either before or after such 
order takes effect, may prescribe by supplemental order such 
terms as it finds to be just and reasonable, including the 
compensation or reimbursement which should be paid to or by any 
such party.
  (2) With respect to an order issued under this subsection 
that may result in a conflict with a requirement of any 
Federal, State, or local environmental law or regulation, the 
Commission shall ensure that such order requires generation, 
delivery, interchange, or transmission of electric energy only 
during hours necessary to meet the emergency and serve the 
public interest, and, to the maximum extent practicable, is 
consistent with any applicable Federal, State, or local 
environmental law or regulation and minimizes any adverse 
environmental impacts.
  (3) To the extent any omission or action taken by a party, 
that is necessary to comply with an order issued under this 
subsection, including any omission or action taken to 
voluntarily comply with such order, results in noncompliance 
with, or causes such party to not comply with, any Federal, 
State, or local environmental law or regulation, such omission 
or action shall not be considered a violation of such 
environmental law or regulation, or subject such party to any 
requirement, civil or criminal liability, or a citizen suit 
under such environmental law or regulation.
  (4)(A) An order issued under this subsection that may result 
in a conflict with a requirement of any Federal, State, or 
local environmental law or regulation shall expire not later 
than 90 days after it is issued. The Commission may renew or 
reissue such order pursuant to paragraphs (1) and (2) for 
subsequent periods, not to exceed 90 days for each period, as 
the Commission determines necessary to meet the emergency and 
serve the public interest.
  (B) In renewing or reissuing an order under subparagraph (A), 
the Commission shall consult with the primary Federal agency 
with expertise in the environmental interest protected by such 
law or regulation, and shall include in any such renewed or 
reissued order such conditions as such Federal agency 
determines necessary to minimize any adverse environmental 
impacts to the extent practicable. The conditions, if any, 
submitted by such Federal agency shall be made available to the 
public. The Commission may exclude such a condition from the 
renewed or reissued order if it determines that such condition 
would prevent the order from adequately addressing the 
emergency necessitating such order and provides in the order, 
or otherwise makes publicly available, an explanation of such 
determination.
  (5) If an order issued under this subsection is subsequently 
stayed, modified, or set aside by a court pursuant to section 
313 or any other provision of law, any omission or action 
previously taken by a party that was necessary to comply with 
the order while the order was in effect, including any omission 
or action taken to voluntarily comply with the order, shall 
remain subject to paragraph (3).
  (d) During the continuance of any emergency requiring 
immediate action, any person or municipality engaged in the 
transmission or sale of electric energy and not otherwise 
subject to the jurisdiction of the Commission may make such 
temporary connections with any public utility subject to the 
jurisdiction of the Commission or may construct such temporary 
facilities for the transmission of electric energy in 
interstate commerce as may be necessary or appropriate to meet 
such emergency, and shall not become subject to the 
jurisdiction of the Commission by reason of such temporary 
connection or temporary construction: Provided, That such 
temporary connection shall be discontinued or such temporary 
construction removed or otherwise disposed of upon the 
termination of such emergency: Provided further, That upon 
approval of the Commission permanent connections for emergency 
use only may be made hereunder.
  [(e) After six months from the date on which this Part takes 
effect, no person shall transmit any electric energy from the 
United States to a foreign country without first having secured 
an order of the Commission authorizing it to do so. The 
Commission shall issue such order upon application unless, 
after opportunity for hearing, it finds that the proposed 
transmission would impair the sufficiency of electric supply 
within the United States or would impede or tend to impede the 
coordination in the public interest of facilities subject to 
the jurisdiction of the Commission. The Commission may by its 
order grant such application in whole or in part, with such 
modifications and upon such terms and conditions as the 
Commission may find necessary or appropriate, and may from time 
to time, after opportunity for hearing and for good cause 
shown, make such supplemental orders in the premises as it may 
find necessary or appropriate.]
  (f) The ownership or operation of facilities for the 
transmission or sale at wholesale of electric energy which is 
(a) generated within a State and transmitted from that State 
across an international boundary and not thereafter transmitted 
into any other State, or (b) generated in a foreign country and 
transmitted across an international boundary into a State and 
not thereafter transmitted into any other State, shall not make 
a person a public utility subject to regulation as such under 
other provisions of this part. The State within which any such 
facilities are located may regulate any such transaction 
[insofar as such State regulation does not conflict with the 
exercise of the Commission's powers under or relating to 
subsection 202(e)].
  (g) In order to insure continuity of service to customers of 
public utilities, the Commission shall require by rule, each 
public utility to--
          (1) report promptly to the Commission and any 
        appropriate State regulatory authorities any 
        anticipated shortage of electric energy or capacity 
        which would affect such utility's capability of serving 
        its wholesale customers,
          (2) submit to the Commission, and to any appropriate 
        State regulatory authority, and periodically revise, 
        contingency plans respecting--
                  (A) shortages of electric energy or capacity, 
                and
                  (B) circumstances which may result in such 
                shortages, and
          (3) accommodate any such shortages or circumstances 
        in a manner which shall--
                  (A) give due consideration to the public 
                health, safety, and welfare, and
                  (B) provide that all persons served directly 
                or indirectly by such public utility will be 
                treated, without undue prejudice or 
                disadvantage.

           *       *       *       *       *       *       *

                              ----------                              


PUBLIC UTILITY REGULATORY POLICIES ACT OF 1978

           *       *       *       *       *       *       *



TITLE VI--MISCELLANEOUS PROVISIONS

           *       *       *       *       *       *       *


SEC. 602. SEASONAL DIVERSITY ELECTRICITY EXCHANGE.

  (a) Authority.--The Secretary may acquire rights-of-way by 
purchase, including eminent domain, through North Dakota, South 
Dakota, and Nebraska for transmission facilities for the 
seasonal diversity exchange of electric power to and from 
Canada if he determines--
          (1) after opportunity for public hearing--
                  (A) that the exchange is in the public 
                interest and would further the purposes 
                referred to in section 101 (1) and (2) of this 
                Act and that the acquisition of such rights-of-
                way and the construction and operation of such 
                transmission facilities for such purposes is 
                otherwise in the public interest,
                  (B) that a permit has been issued in 
                accordance with subsection (b) for such 
                construction, operation, maintenance, and 
                connection of the facilities at the border for 
                the transmission of electric energy between the 
                United States and Canada as is necessary for 
                such exchange of electric power, and
                  (C) that each affected State has approved the 
                portion of the transmission route located in 
                each State in accordance with applicable State 
                law, or if there is no such applicable State 
                law in such State, the Governor has approved 
                such portion; and
          (2) after consultation with the Secretary of the 
        Interior and the heads of other affected Federal 
        agencies, that the Secretary of the Interior and the 
        heads of such, other agencies concur in writing in the 
        location of such portion of the transmission facilities 
        as crosses Federal land under the jurisdiction of such 
        Secretary or such other Federal agency, as the case may 
        be.
The Secretary shall provide to any State such cooperation and 
technical assistance as the State may request and as he 
determines appropriate in the selection of a transmission 
route. If the transmission route approved by any State does not 
appear to be feasible and in the public interest, the Secretary 
shall encourage such State to review such route and to develop 
a route that is feasible and in the public interest. Any 
exercise by the Secretary of the power of eminent domain under 
this section shall be in accordance with other applicable 
provisions of Federal law. The Secretary shall provide public 
notice of his intention to acquire any right-of-way before 
exercising such power of eminent domain with respect to such 
right-of-way.
  (b) Permit.--Notwithstanding any transfer of functions under 
the first sentence of section 301(b) of the Department of 
Energy Organization Act, no permit referred to in subsection 
(a)(1)(B) may be issued unless [the Commission has conducted 
hearings and made the findings required under section 202(e) of 
the Federal Power Act and under the applicable execution order 
respecting the construction, operation, maintenance, or 
connection at the borders of the United States of facilities 
for the transmission of electric energy between the United 
States and a foreign country. Any finding of the Commission 
under an applicable executive order referred to in this 
subsection shall be treated for purposes of judicial review as 
an order issued under section 202(e) of the Federal Power Act.] 
the Secretary has conducted hearings and finds that the 
proposed transmission facilities would not impair the 
sufficiency of electric supply within the United States or 
would not impede or tend to impede the coordination in the 
public interest of facilities subject to the jurisdiction of 
the Secretary.
  (c) Timely Acquisition by Other Means.--The Secretary may not 
acquire any rights-of-day under this section unless he 
determines that the holder or holders of a permit referred to 
in subsection (a)(1)(B) are unable to acquire such rights-of-
way under State condemnation authority, or after reasonable 
opportunity for negotiation, without unreasonably delaying 
construction, taking into consideration the impact of such 
delay on completion of the facilities in a timely fashion.
  (d) Payments by Permittees.--(1) The property interest 
acquired by the Secretary under this section (whether by 
eminent domain or other purchase) shall be transferred by the 
Secretary to the holder of a permit referred to in subsection 
(b) if such holder has made payment to the Secretary of the 
entire costs of the acquisition of such property interest, 
including administrative costs. The Secretary may accept, and 
expend, for purposes of such acquisition, amounts from any such 
person before acquiring a property interest to be transferred 
to such person under this section.
  (2) If no payment is made by a permit holder under paragraph 
(1), within a reasonable time, the Secretary shall offer such 
rights-of-way to the original owner for reacquisition at the 
original price paid by the Secretary. If such original owner 
refuses to reacquire such property after a reasonable period, 
the Secretary shall dispose of such property in accordance with 
applicable provisions of law governing disposal of property of 
the United States.
  (e) Federal Law Governing Federal Lands.--This section shall 
not affect any Federal law governing Federal lands.
  (f) Reports.--The Secretary shall report annually to the 
Congress on the actions, if any, taken pursuant to this 
section.

           *       *       *       *       *       *       *

[GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT]


                            DISSENTING VIEWS

    H.R. 2883 would substantially weaken the process for 
federal approval of oil and natural gas pipelines and electric 
transmission lines that cross the U.S. border with Canada or 
Mexico. The new process established by the bill effectively 
exempts such projects from environmental and safety review 
under the National Environmental Policy Act (NEPA) by narrowing 
NEPA applicability to just the sliver of the project actually 
crossing the border. The process created by the bill also tips 
the scales too far in favor of promoters of controversial 
projects by establishing a rebuttable presumption that said 
projects are to be approved. H.R. 2883 would allow a project 
that is found not to be in the public interest under the 
current permitting process to reapply under the new weaker 
process. The bill would exempt all modifications to existing 
cross-border pipelines, including major expansions of 
pipelines, from any requirement for federal review or approval.
    The effect of these changes will allow large and long-lived 
cross-border energy projects to be approved with no 
understanding or consideration of their environmental impacts. 
In fact, such projects could even be exempted from any 
permitting requirement at all. The public, including 
communities and landowners directly affected by the projects, 
would have scarce to absolutely no information and be left 
without any opportunity to object or request mitigating action, 
except to the extent some limited recourse can be located and 
pursued through state law.

      CURRENT PERMITTING PROCESS FOR TRANSBOUNDARY ENERGY PROJECTS

    Proposed oil pipelines, natural gas pipelines, and electric 
transmission lines that cross the U.S. boundary with Mexico or 
Canada must obtain presidential permits pursuant to executive 
orders.\1\ Additional statutory requirements apply to trans-
boundary, natural gas pipelines and electric transmission 
lines, as well as to exports of natural gas and electricity.
---------------------------------------------------------------------------
    \1\The executive branch authority to issue presidential permits for 
cross-border energy project derives from the President's constitutional 
authority to conduct foreign affairs. See Congressional Research 
Service, Presidential Permits for Border Crossing Energy Facilities 
(Mar. 15, 2017) (R43261).
---------------------------------------------------------------------------
Oil Pipelines
    The President has delegated authority to permit cross-
border oil pipeline projects to the State Department, which is 
required to make an affirmative finding that a project is in 
the national interest.\2\ Prior to making the national interest 
determination, NEPA requires the State Department to prepare, 
with notice and public comment, an environmental impact 
statement on a project and evaluate alternatives that would 
avoid or minimize adverse environmental effects.\3\
---------------------------------------------------------------------------
    \2\Exec. Order No. 11423, 33 Fed. Reg. 11741 (Aug. 16, 1968); Exec. 
Order No. 13337, 69 Fed. Reg. 25299 (Apr. 30, 2004).
    \3\National Environmental Policy Act of 1969, Pub. L. No. 94-83.
---------------------------------------------------------------------------
Natural Gas Pipelines and Exports
    The Federal Energy Regulatory Commission (FERC) is 
authorized to issue a presidential permit if it finds a natural 
gas pipeline project ``to be consistent with the public 
interest'' and receives favorable recommendations from the 
Secretary of State and Secretary of Defense.\4\ FERC may set 
conditions on a permit to protect the public interest. A cross-
border natural gas pipeline must also obtain FERC approval 
under section 3 of the Natural Gas Act (NGA), as well as 
favorable recommendations by the State and Defense Departments. 
FERC must grant an application unless it finds that the 
proposed export will not be consistent with the public 
interest. Under FERC's regulations, an applicant applies for 
the Natural Gas Act approval and the presidential permit 
simultaneously in a single application package. One 
environmental review is performed for the entire submission.
---------------------------------------------------------------------------
    \4\Exec. Order No. 10485, 18 Fed. Reg. 5397 (Sept. 3, 1953).
---------------------------------------------------------------------------
    An entity seeking to export natural gas as a commodity 
through a pipeline or as liquefied natural gas (LNG) must 
obtain approval from the Department of Energy (DOE). For export 
to Canada, Mexico and other countries with a free trade 
agreement, the NGA requires DOE to deem such applications 
consistent with the public interest and grant them without 
modification or delay.
Electric Transmission Lines and Electricity Exports
    DOE is authorized to issue a presidential permit if it 
finds the electric transmission line project ``to be consistent 
with the public interest'' and receives favorable 
recommendations from the Secretary of State and Secretary of 
Defense.\5\ DOE makes the public interest determination ``by 
evaluating the electric reliability impacts, the potential 
environmental impacts, and any other factors that DOE may also 
consider relevant to the public interest.''\6\ An environmental 
analysis is required to comply with NEPA. DOE may set 
conditions on a permit to protect the public interest. 
Additionally, under section 202(e) of the Federal Power Act 
(FPA), the transmission of electricity from the U.S. to another 
country requires approval from DOE. DOE is required to approve 
an application unless it finds that the proposed transmission 
of electricity would ``impair the sufficiency of electric 
supply within the United States or would impede or tend to 
impede the coordination in the public interest of [electric] 
facilities.''\7\ DOE may set conditions on the approval.
---------------------------------------------------------------------------
    \5\Exec. Order No. 10485, 18 Fed. Reg. 5397 (Sept. 3, 1953).
    \6\U.S. Department of Energy, Interpretative Guidance on the 
Requirements of 10 C.F.R. Sec. 205.322 (Jun. 2, 2011).
    \7\Federal Power Act Sec. 202(e); 16 U.S.C. 824 a(e).
---------------------------------------------------------------------------

                                ANALYSIS

    The new approval process established in section 2(a)(2)of 
the legislation requires the relevant official to issue a 
``certificate of crossing'' for a border-crossing facility 
within 120 days of final action under NEPA, unless the official 
finds that the project ``is not in the public interest of the 
United States.'' This language replaces the existing federal 
approval process that requires a presidential permit for the 
entire trans-boundary project, not just a segment. The relevant 
officials are FERC for oil and natural gas pipelines, and the 
Secretary of Energy for electric transmission lines. Moving the 
responsibility for approval of oil pipelines to FERC could lead 
to delays since FERC currently has no authority or experience 
with the siting of oil pipelines.
    Unlike the existing process, this provision establishes a 
rebuttable presumption of approval, tipping the scale in favor 
of the project. Instead of requiring an agency to affirmatively 
find that a project is in the public interest, it shifts the 
burden of proof to opponents of the project to show that it is 
not in the public interest. Further a ``border-crossing 
facility'' is defined as the portion of the project ``that is 
located at an international boundary of the United States.'' 
These trans-boundary projects are multi-billion dollar 
infrastructure investments that can stretch hundreds of miles 
and last for decades. Before making decisions about whether to 
approve such projects, federal agencies should be required to 
carefully consider their potential impacts on the environment 
and on communities along their routes. However, this language 
limits the scope of review for federal approval to just a 
sliver of a much larger project and makes it extremely 
difficult--if not impossible--for an agency to prove an 
application as contrary to the public interest.
    Section 2(a)(3) temporarily excludes from the new 
permitting process any cross-border project with permit 
approval pending on the date of enactment. This exclusion ends 
when the application is denied, or two years later for any 
application still pending. This provision would give 
controversial projects incentive to simply wait until the 
exclusion expires, and would give any project denied a 
presidential permit a second bite at the apple under the new, 
rubber-stamp process.
    Subsection (b) amends section 3 of the Natural Gas Act to 
require DOE to grant authorization for the export or import of 
LNG to or from Canada or Mexico, within 30 days. Currently, 
companies wishing to export LNG to Canada or Mexico must obtain 
federal approval before doing so. These applications are 
relatively simple filings, and approvals can include 
conditions, such as prohibitions against simply using Canada or 
Mexico as a pass-through before shipping the gas to another 
country. This provision sets a deadline for DOE to grant 
authorization, but provides no mechanism for a deadline 
extension. If DOE is faced with rigid deadlines it cannot meet, 
the result will likely be unnecessary application denials 
rather than expedited approvals.
    Subsection (c) of the bill repeals FPA section 202(e), 
which requires approval from DOE for the transmission of 
electricity from the U.S. to another country. This could 
significantly disrupt electricity and transmission markets by 
undermining FERC's ability to ensure non-discriminatory open 
access to the transmission grid. Owners of trans-boundary 
transmission lines could demand discriminatory charges when 
providing service across the U.S. border with Canada or Mexico, 
or deny access altogether.
    Subsection (e) says that no certificate of crossing or 
presidential permit is required for modifications to existing 
projects. Under this subsection, modifications include a change 
in ownership, volume expansion, downstream or upstream 
interconnection, or adjustments to maintain flow (such as an 
increase or decrease in the number of pump or compressor 
stations). Many modifications, as defined by this bill, could 
have impacts just as significant as those resulting from an 
entirely new project. But, as a result of this language, 
controversial modifications to existing cross-border pipelines 
or transmission lines would not require federal approval and 
would not be subject to any environmental review.
    The provisions of H.R. 2883 raise significant concerns, so 
during Full Committee markup, Full Committee Ranking Member 
Pallone and Energy Subcommittee Ranking Member Rush offered 
amendments to address two of the major issues with the bill. 
The Pallone amendment removed the limitation on NEPA review to 
only the border-crossing facility, and the Rush amendment 
removed the presumption of approval language. Neither of these 
amendments were adopted.
    For the reasons stated above, we dissent from the views 
contained in the Committee's report.

                                   Frank Pallone, Jr.,
                                           Ranking Member.
                                   Bobby L. Rush,
                                           Ranking Member, Subcommittee 
                                               on Energy.

                                  [all]