NYS Thruway Authority: Thruway Authority to Continue with Tappan Zee Bridge Deck Replacement Project

TARRYTOWN, NY -- Deck replacement work on the Tappan Zee Bridge will continue during the week of July 2, 2012, the New York State Thruway Authority announced.

The work will be done in sequential order, is weather-dependent, and is subject to change. Updates will be issued to announce any change in schedule.

 

Monday, July 2

Work will begin at 8 p.m. resulting in the closure of two left southbound lanes and an additional left southbound lane at 11 p.m. until 6 a.m., from milepost 13.2 to milepost 17.9 on theTappan Zee Bridge. In addition, this will result in the closure of one left northbound lane at 9 p.m., and an additional left northbound lane at 11 p.m. until 6 a.m. from milepost 13.2 to milepost 16.2, also on the Tappan Zee Bridge. At least one lane southbound will be opened to traffic from 8 p.m. to 6 a.m. and one lane northbound will be opened to traffic from 9 p.m. to 6 a.m.

During Monday night operations, due to the southbound lane closures, the southbound entrance at Interchange 10 will be closed from 8 p.m. to 6 a.m. and southbound detour route signs will be posted through Nyack for the entrance at Route 59 near Interchange 11.

During Monday night operations, due to the northbound lane closures, the entrance ramp from Broadway (southbound) inTarrytown will also be closed from 9 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Tuesday, July 3

No work scheduled on Tuesday night.

Wednesday, July 4

No work scheduled.

Thursday, July 5

Work will begin at 8 p.m. resulting in the closure of two left southbound lanes and an additional left southbound lane at 11 p.m. until 6 a.m. from milepost 13.2 to milepost 17.9 on theTappan Zee Bridge. In addition, this will result in the closure of one left northbound lane at 10 p.m. and an additional left northbound lane at 12 midnight until 6 a.m. from milepost 13.2 to milepost 16.2 also on the Tappan Zee Bridge. At least one lane southbound will be opened to traffic from 8 p.m. to 6 a.m. and one lane northbound will be opened to traffic from 10 p.m. to 6 a.m.

During Thursday night operations, due to the southbound lane closures, the southbound entrance at Interchange 10 will be closed from 8 p.m. to 6 a.m. and southbound detour route signs will be posted through Nyack for the entrance at Route 59 near Interchange 11.

During Thursday night operations, due to the northbound lane closures, the entrance ramp from Broadway (southbound) inTarrytown will also be closed from 10 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Friday, July 6 and Saturday, July 7

Work will begin at 9 p.m. resulting in the closure of two left southbound lanes and an additional left southbound lane at 12 Midnight until 7 a.m., from milepost 13.2 to milepost 17.9 on the Tappan Zee Bridge. In addition, this will result in the closure of one left northbound lane at 10 p.m. and an additional left northbound lane at 12 midnight until 7 a.m. from milepost 13.2 to milepost 16.2 also on the Tappan Zee Bridge. At least one lane southbound will be opened to traffic from 9 p.m. to 7 a.m., and one lane northbound will be opened to traffic from 10 p.m. to 7 a.m.

During Friday night operations, due to the southbound lane closures, the southbound entrance at Interchange 10 will be closed from 9 p.m. to 7 a.m. and southbound detour route signs will be posted through Nyack for the entrance at Route 59 near Interchange 11.

During Friday night operations, due to the northbound lane closures, the entrance ramp from Broadway (southbound) inTarrytown will also be closed from 10 p.m. until 7 a.m. All traffic will be detoured to the entrance ramp from Route 119.

No work scheduled for Saturday night.

Sunday, July 8

No work scheduled.

The lane closures on Monday, Thursday and Friday nights are required in order for the contractor to continue with the replacement of the deck in the middle three lanes on the Tappan Zee Bridge from milepost 13.2 to milepost 17.9.

During the nighttime operations, several 20 minutes traffic stoppages will take place in both the northbound and southbound directions.

For the safety of the public and construction workers, motorists are urged to proceed with caution and obey posted work-zone speed limits.

Traffic updates will be broadcast to motorists via Variable Message Signs along the highway and by Highway Advisory Radio 530 AM in the Tappan Zee Bridge corridor, as well as 1610 AM in the Newburgh area.

The second phase of the deck replacement project is slated for completion in the winter of 2012.

The original press release can be found here.