STATEMENT OF

MONTGOMERY FISCHER

POLICY DIRECTOR FOR WATER RESOURCES

NATIONAL WILDLIFE FEDERATION

FOR HEARING ON

PROPOSALS FOR A WATER RESOURCES DEVELOPMENT ACT OF 2002

BEFORE THE

COMMITTEE ON ENVIRONMENT AND PUBLIC WORKS

UNITED STATES SENATE

JUNE 18, 2002

 

On behalf of the National Wildlife Federation (NWF), I would like to thank the Chairman, Ranking Member and the members of the Committee for the opportunity to present the Federation=s views on issues pertaining to water resources development programs of the U.S. Army Corps of Engineers.

 

I am Montgomery Fischer, Policy Director for Water Resources at the National Wildlife Federation. We are the nation's largest not-for-profit conservation, education, and advocacy organization with more than four million members and supporters and nine natural resource centers throughout the United States. The National Wildlife Federation's family also includes forty-six state and territorial affiliate conservation organizations. Founded in 1936, the National Wildlife Federation works for the protection of wildlife species and their habitat, and for the conservation of our natural resources. With a graduate degree in Soil and Water Science from the University of New Hampshire in Durham, my personal work with water resources protection spans three decades, including working as a commercial fisherman as well as in the government, academic, and non-profit sectors.

 

The National Wildlife Federation and our affiliates have a long history of interest and involvement with the development of our nation=s water resources, particularly as it relates to projects and programs of the U.S. Army Corps of Engineers.

 

Much of our nation=s wildlife is dependent on critical aquatic habitat, which includes rivers, streams, bays, estuaries, wetlands and coastlines. But, our wildlife resources are hurting. Artificially altering waterways B along with water pollution and introduction of foreign species B have been identified by the scientific community as the principal causes of the shocking state of decline of aquatic ecosystems and wildlife that has been experienced in many regions across the country. Through its Civil Works and regulatory programs, the U.S. Army Corps of Engineers has a profound impact on the health of aquatic ecosystems. While much of the Corps= work in the 20th Century has had devastating impacts on the natural environment, NWF believes that with the right direction from Congress, the 21st Century Corps can become the premier federal agency for restoring and protecting our nation=s aquatic ecosystems and the species that depend on them. The Corps= efforts to restore the Florida Everglades is a prime example of the type of restoration work the Corps should focus on during this Century.

 

As this Committee considers proposals for a Water Resources Development Act (WRDA), a fundamental goal must be to address the serious and growing crisis in confidence that much of the American public has about the Corps of Engineers. A series of recent reports and investigations over the past several years by policy experts and scientists have found that the Corps= planning process for major water resource projects is failing in fundamental ways to address contemporary needs of communities and regions in an environmentally sound and cost effective manner. A Water Resources Development Act presents Congress with a critical opportunity to provide the Corps greater oversight and clearer direction to meet the nation=s water resource needs and to restore confidence in this agency.

 

NWF congratulates the Ranking Member of this Committee and other Senators who have sponsored legislation that would make critical, common sense reforms in Corps programs B particularly, S. 1987, the Corps of Engineers Modernization and Improvement Act of 2002, and S. 646, the Corps of Engineers Reform Act of 2001.


WRDA SHOULD NOT MOVE FORWARD WITHOUT CORPS REFORM.

The National Wildlife Federation strongly supports both S. 1987 and S. 646 because these bills contain critically needed reforms to improve and modernize the way the Corps responds to the nation=s water resources development needs and  to ensure every project the Corps undertakes represents a sound, environmentally sustainable investment. The bills improve the Corps= accountability, modernize its principles and practices, improve mitigation of wetlands, pull the plug on projects that no longer make sense, keep federal costs down, and stop the Arace to the bottom@ among ports and harbors.

 

Improve Accountability.  S. 1987 and S. 646 would make the Corps more accountable to help restore the public=s confidence in this agency by:

_   requiring independent peer review for costly projects and controversial projects;

_   enhancing the public=s ability to participate in the Corps= planning process; and

_   increasing the public=s access to information.

 

Modernize the Corps.  S. 1987 and S. 646 would modernize the Corps= basic approach to developing and planning water resources projects by:

_   directing that the Principles & Guidelines be revised and updated to define environmental protection and restoration as a co-equal goal with economic development, and to incorporate other changes that ensure this goal is carried out; and

_   modernizing the basic criteria used by the Corps to justify moving forward with a project.

 

Wetlands Mitigation Improvement. 

_    S. 646 would improve the way the Corps mitigates for wetlands impacted by Corps projects; and

_    both S. 646 and S. 1987 would exclude from economic justification analyses benefits derived from draining wetlands.

 

Pull the Plug on Outdated Projects.  S.1987 would help prioritize the Corps= efforts by:

_   expediting the automatic deauthorization process to reduce the Corps= burgeoning backlog; and

_   updating the Corps= benefit-to-cost ratios to ensure taxpayers get a better return on their investment.

 

Keep Federal Costs Down.  S. 1987 would reduce the federal government=s burden for sand pumping projects.

 

Stop the Race to the Bottom.  S. 1987 would improve the way the Corps plans to deepen ports and harbors by requiring regional port planning.

 


Given the record of problems that has amassed over the past several years, the Corps should not be allowed to continue with business as usual. The problems are so grave, a WRDA should not move forward without these reforms. I will now spend a few minutes discussing some of the problems that have plagued the Corps and that the bills seek to address.

 

CORPS CRISIS IN PUBLIC CONFIDENCE.

 

There Is No Effective, Independent Technical and Policy Review of Corps Projects.

 

Mr. Chairman, among the most critical issues that must be addressed in any potential WRDA is the establishment of an effective, independent system of technical and policy review by outside experts for Corps of Engineers projects.  For years, the public, other federal and state agencies, academicians and scientists, government auditors, and many Members of Congress have questioned the accuracy of Corps planning documents, and, in some cases, whether under the present system, the Corps is capable of being truly objective in planning its projects. In the 1980s, the General Accounting Office identified numerous serious issues in this regard. A critical means to help ensure objectivity in the planning process is to formally engage outside experts to conduct public reviews of Corps plans and their underlying studies and assumptions.

 

In recent years, the number of major concerns regarding the quality and accuracy of Corps plans has increased in both seriousness and number, and the need for independent review has become increasingly clear. During the 1990s, several factors converged to bring about this situation.

 

Changes in the Review Process.

 

Since the early 1990s, the level of effective project review has dramatically decreased within the Corps. In part, this is in response to continuing calls for Astreamlining@ the planning process and changes in the general focus of the Corps to operate more as a service agent, particularly to local project sponsors.

 

Over the past decade, the Corps has instituted substantial changes that have greatly weakened what was already a weak and inadequate review process. Up to the early 1990s, the primary mechanism for independent review was the congressionally established Board of Engineers for Rivers and Harbors. This Board, consisting primarily of Division Engineers, and supported by a staff of 30 to 40 professional project reviewers, was independent of Corps Headquarters management, and had the job of top-to-bottom review of all new Corps project proposals. In WRDA 1992, however, in an effort to cut expenses and improve efficiency, the Board was abolished, and the professional staff was reorganized into a Washington Level Review Center, still organizationally outside the Headquarters Division of Civil Works. In 1995, in another reorganization, the Review Center became a Review Branch within the Headquarters Division of Civil Works. The staff was cut from 35 to about 24, and their responsibilities were substantially expanded to include other duties.

 


In a series of steps, the responsibility for project technical reviews was devolved to the Corps Districts themselves, and the Washington level review became focused on policy compliance only. The District-level technical reviews are generally conducted by peer staff or are focused on reviewing the work of Corps contractors. Two years ago, in yet another reorganization, the Project Review Branch became the Policy Compliance Support Branch and the Washington level review staff was cut back to a dozen.

 

Time frames for review have been cut to a minimum with final reviews by other federal agencies and states running concurrently with that of Corps headquarters. In recent years, many Corps Districts rush to complete project plans in order to seek Acontingent authorization@ in even-years for inclusion in WRDA bills, which puts immense and inordinate pressure on the Corps to approve projects while deferring many studies and often deferring serious unresolved issues until after construction authorization.

 

The result of all this reorganization has been a substantial reduction in resources and emphasis on critical review of projects within the Corps.  The devolution of much oversight to the local District level B where the greatest pressures exist to justify the projects sought by local sponsors and promoters B often comes at a far greater ultimate cost to the taxpayers and the environment than it should.

 

Lessons From the Upper Mississippi River.

 

The case of the potential $1.2 billion Upper Mississippi River Navigation Expansion project illustrates the strong need for a system of truly independent review, outside of the agency. The $56 million study to expand a system of locks and dams on the Upper Mississippi River was among the most expensive in Corps history. It became the subject of an Army Inspector General investigation after a Corps economist alleged that the books had been cooked in order to justify the project. In addition, the Department of Defense requested that the National Academy of Sciences (NAS) review the economic analysis in the Corps= feasibility report. The Army Inspector General and the NAS found evidence of bias in the planning process, utter failure by the Corps to evaluate alternatives to large-scale construction that would be less expensive and less environmentally damaging, such as scheduling and tolls, and flawed economic analysis.

 

The Army Inspector General=s November 2000 investigation found: ANearly all the economists expressed a view that the Corps (or individuals within the Corps) held an inherent preference for large scale construction.@ The Inspector General made clear that problems were not limited to a single project, but in fact, agency-wide: AAlthough this investigation focused on one study, the testimony and evidence presented strong indications that institutional bias might extend throughout the Corps. Advocacy, growth, the customer service model, and the Corps reliance on external funding combined to create an atmosphere where objectivity in its analyses was placed in jeopardy.@ In addition, the report concluded, AThe overall impression conveyed by testimony of Corps employees was that some of them had no confidence in the integrity of the Corps study process.@

 

In the follow-up February 2001 report of the National Academy of Sciences, Inland Navigation System Planning: The Upper Mississippi River B Illinois Waterway, the NAS recommended:  AThe feasibility study would benefit from a second opinion from an independent, expert, and interdisciplinary body from outside the Corps of Engineers and Department of Defense.  Congress should thus direct the Corps to have the waterway system management and lock extension feasibility study reviewed by an interdisciplinary group of experts B including environmental and social scientists B from outside the Corps of Engineers.@


 

The Corps has attempted to diffuse the significance of the Inspector General and NAS findings in the Upper Mississippi River Navigation Expansion case by stating that the feasibility study was in draft form. This argument may have carried some credibility if there were a strong independent review process in place. But as just explained, that process has been weakened severely B without the Inspector General or the NAS, there is no guarantee that anyone would have checked the Corps= math. Since then, the Corps has rescoped the Upper Mississippi Navigation study and is now engaged in a collaborative process with other state and federal resource agencies and stakeholders to identify a comprehensive range of issues and potential solutions that address navigation and the environment. NWF would strongly oppose any attempts to prematurely authorize construction of the expansion project before the Corps submits a completed report to Congress. A comprehensive approach must not focus solely on the transportation issues without addressing the very serious environmental impacts associated with the project. An authorization request at this time is nothing more than an attempt to once again short-circuit the planning process.

 

GAO Report on Delaware River Main Channel Deepening.

Mr. Chairman, the findings of the General Accounting Office=s (GAO) report, Delaware River Deepening Project -- Comprehensive Reanalysis Needed, (GAO-02-604, June 2002), released last week, demonstrate a fundamental breakdown of the Corps= internal project review process. In the case of this $420 million navigation dredging proposal, the GAO concluded that Corps review was Aineffective@ and Adoes not provide a reliable basis for deciding whether to proceed with the project.@ In March of 2000, the National Wildlife Federation and Taxpayers for Common Sense identified this project as the number two worst Corps project in our report, Troubled Waters, because of extremely questionable economic justification and potential environmental threats to the Delaware Bay region, yet the Corps continued to claim the project was completely and properly justified.  

 

The GAO found that despite the Corps= claims of  $40.1 million in annual benefits from the project (largely from transportation savings to shippers), only $13.3 million in annual benefits had Acredible support.@ The Corps= economic justification was fraught with Amiscalculations, invalid assumptions, and the use of significantly outdated information.@ The Corps greatly overstated benefits based upon improperly double-counted time savings for shippers in both the Delaware Bay and in foreign ports, Amiscalculated trade route distances,@ blamed certain unjustified benefits on Acomputer error@, hugely overestimated crude oil and scrap metal traffic projections, and utterly failed to make the required adjustments in benefit projections during the 1990s to reflect shipping realities, among many other fundamental errors.

 

No stronger case could be made for the need for basic reform of the project review process.

 

Other Examples of Projects Under Investigation.

 

As documented by the Inspector General, NAS and GAO reports, problems within the Corps= planning process are not limited to a single project study. Other examples of where the Corps= planning process has failed or is currently under serious investigation include:

 


_    The Oregon Inlet Jetties Project in North Carolina is also the subject of a General Accounting Office investigation. There, the Corps has continually refused to consider alternatives to constructing stone jetties on environmentally significant public lands on North Carolina=s Outer Banks, despite more than two decades of objections from other responsible federal agencies and independent economists, who believe the Corps economic justification is false. This project is also subject to a referral to the President=s Council on Environmental Quality.

 

_    Savannah Harbor Expansion Project in Georgia received contingent authorization for $230 million of construction in 1999. The Chief of Engineers approved the project despite numerous basic environmental and economic issues that were left unresolved over the objections of other federal and state agencies and the State of South Carolina to post-construction authorization. The project is now a subject of litigation and the Corps is undertaking a major new planning study.

 

_    Dallas Floodway Extension Project in Texas is yet another example of where the Corps has refused to give serious consideration to a less costly and more environmentally friendly alternative, involving buy-outs and voluntary relocations being sought by a lower income community in south Dallas. Last year, the Office of Management and Budget concluded that the Corps had failed to follow its own planning guidelines and rules in designing the $140 million (2001 dollars) project by not identifying the most cost-effective alternative consistent with protecting the environment. This spring, a U.S. District Court ruled that the Corps= environmental analysis failed to comply with the National Environmental Policy Act because the Corps did not analyze the cumulative effects of the project with other activities planned in the area. The Administration has refused to budget this project and the Court ordered the Corps to cease work until it has completed evaluating the cumulative environmental impacts.

 

_    Projects in the Lower Mississippi River Basin, such as the Yazoo Pumps and the Big Sunflower River Dredging Project in the State of Mississippi would cost more than $200 million and threaten to destroy hundreds of thousands of wetlands acres, even though less costly and more environmentally sound options exist to reduce flood damage risks in the region. An independent economic analysis of the Corps= Yazoo Backwater pumping plant in Mississippi, revealed that the Corps overestimated just the agricultural benefits of that project by $144 million, and that even if all of the remaining benefit calculations were correct, it could not justify construction of the project. For the Big Sunflower Project, the U.S. Fish and Wildlife Service found that the Corps significantly overestimated the costs of purchasing easements, which could achieve the project objectives without dredging.

 


_    Columbia River Deepening Project was recently the subject of a six-month investigation by a Portland newspaper, which found that the Corps had overestimated project benefits by 140 percent, and that the benefits only amount to 88 cents on the dollar. The proposed dredging of 103 miles of the lower Columbia has also raised huge questions about the Corps= proposed mitigation for water quality and wetlands impacts, and impacts to salmon and other sport and commercial fisheries habitats. After the newspaper stories ran the Corps agreed to review its economic analysis.

 

Independent Project Review Would Strengthen the Corps= Program.

At a minimum, Congress should require that studies of all Corps projects representing a significant investment of taxpayer dollars, and studies of all projects that generate controversy because of threats posed to the environment be reviewed by a panel of qualified and independent experts in various fields, such as economics, engineering, biology, geology and hydrology. This type of review can take place without delaying the overall planning process for justified projects, and would help to restore confidence in the process. Perhaps most importantly, a system of independent project review would provide the Corps= own study preparers with a strong incentive to resist pressures to Acook the books.@ It would help to ensure that the Corps projects that do proceed to construction are the best they can be. NWF strongly supports implementing a system of independent project review, which is a critical element in each of the Corps reform bills, S. 646 and S. 1987.

 

Corps= Approach to Planning and Developing Water Resource Projects Gives Short Shrift to the Environment.

 

Among the key findings of recent National Academy of Sciences reports are the need for the Corps= planning process to be updated to reflect current economic and environmental procedures and approaches to water resources development and management. The 1999 report, New Directions in Water Resources Planning for the U.S. Army Corps of Engineers, points out that the 1983 Principles and Guidelines for Water and Related Land Resources Implementation Studies (AP&G@) have been frozen in time for almost 20 years. At the same time, economic and environmental sciences have increasingly evolved sophisticated methodologies to evaluate benefits and costs of structural and nonstructural approaches in response to changing public needs and attitudes toward the environment and natural resources.

 

The need to amend the P&G to require that national economic development and environmental protection and restoration be afforded co-equal status in the formulation of Corps of Engineers projects is even more relevant today than it was when the NAS made the recommendation three years ago. This is a fundamental change that is needed in the Corps= project planning that must be included in any future Water Resources Development Act. 

 

Update the P&G to Reflect 21st Century Principles and Practices.

 

The NAS 1999 New Directions report recommended updating the P&G, including these specific examples:

 

(1)            Movement away from consideration of the National Economic Development (NED) account as the most important concern in order to encourage consideration of innovative and nonstructural approaches to water resource planning, which can often better address ecological and social concerns.


(2)            Many aspects of the Corps= environmental programs are not reflected in the P&G requirements because they were enacted after the P&G was approved in 1983. The P&G needs to be updated to reflect these new and important Corps programs.

(3)            The P&G should be updated to reflect new advances and techniques for risk and uncertainty analysis.

(4)            The P&G should be updated to eliminate biases or disincentives that work against nonstructural approaches, and to ensure that the benefits of flood damages avoided by nonstructural projects are consistently and uniformly considered.

 

The P&G were written by the Water Resources Council (WRC), which was created in the 1960s to coordinate the formulation and execution of federal water policies. The WRC is dormant today because of lack of funding.  The lack of procedural clarity for how to update the P&G should be eliminated by identifying a clear mechanism for review. 

 

The Corps= customer-service model, aimed at providing services to local communities that are sharing the cost of a project, is undermining the Corps= responsibility to promote the national interest in its water planning activities.  To promote efficient plans and projects across the nation=s river basin systems, the Corps should use the watershed or river basin, estuarial region, and coastal unit as the basic spatial units in water project planning, when and where it is appropriate and circumstances allow. The use of such hydrologic units for planning can help account for downstream effects of flood damage reduction projects, for example, or provide a system to account for cumulative effects of Corps projects.  Most of the nation=s large river basins cross state lines, which requires federal involvement to store and manage data, model hydrology and analyze system-wide impacts.

 

The 1999 New Directions report strongly recommends modernizing and revising the P&G, and requiring that ecosystem protection and restoration be established as co-equal goals with economic development. The report also recommends that Corps planning be more oriented to watershed and regional perspectives, particularly where projects have significant upstream and downstream impacts, or for functions that serve or impact regions, such as ports and harbors. Advances in scientific knowledge, ecological sciences, and economic analytic techniques should be further incorporated in Corps planning procedures. A growing cry of support for these changes is coming from states and professional societies as among the greatest failings of Corps water resources development programs.

 

Several of these key elements are included in S. 646 and S. 1987, and we strongly urge that these provisions be incorporated into WRDA legislation.

 

Corps Projects Continue to Threaten Enormous Amounts of the Nation=s Critical Wetland Resources and the Corps Fails to Mitigate Losses.

 

The National Wildlife Federation is very concerned about the Corps= growing backlog of mitigation for Civil Works projects. Although the Corps is required to mitigate for wetlands lost as a result of a Civil Works project, the existence of a growing mitigation backlog means that the mitigation is not being done and the environment is suffering.

 


Despite requirements that mitigation occur concurrently with Civil Works projects, the Corps has failed to follow through on significant amounts of acres of mitigation required for projects that are well underway, or for all practical purposes, completed. For example, in the Lower Mississippi River Valley, the Corps has been authorized to purchase tens of thousands of acres of mitigation land that have not been purchased. The mitigation backlog in the Vicksburg District alone currently exceeds 28,000 acres. The time lag in completing mitigation for water resources projects is resulting in an enormous temporal loss of wetland functions and values in many valuable and vulnerable watersheds.

 

Ironically, the Corps reports that permits issued under the entire Section 404 dredge and fill permit program of the Clean Water Act account for 24,000 acres of direct wetlands loss per year. The U.S. Fish and Wildlife Service estimates that on average just under 30,000 acres of wetlands were lost each year between 1987 and 1997 from urban and rural development. Yet the Corps Civil Works program currently threatens 300,000 acres of critical bottomland hardwood losses from just a handful of projects that are among the most controversial in the nation to reduce flooding in what are often low-lying areas in two-year floodplains to promote marginal soy bean production. We urge the Committee to help redirect the Corps away from such activities that are environmentally damaging to wetlands and toward programs that would help rural economies benefit from restoring wetland resources and develop sound, sustainable economies that benefit from these special resources.

 

Improvements in Wetlands Mitigation.

NWF strongly supports the wetland mitigation provisions of S. 646, which would clarify the definition of concurrent mitigation and improve the standards for mitigation, including improving the probability of cost-effectively and successfully mitigating habitat losses. In addition, S. 646 would address the mitigation backlog by requiring the Corps to establish a tracking system to identify the status of mitigation.

 

We further recommend that the Corps prepare a Mitigation Backlog Management Plan that is updated each year and will enable the Corps to eliminate its backlog of mitigation by seeking to have lands in place by FY 2005, and future schedules for initiating and completing mitigation activities in a timely fashion. Further, as proposed in S. 646, new requirements should be placed upon mitigation for Corps Civil Works projects to ensure that at least 50 percent of mitigation is completed in advance of the start of construction, with mitigation to be completed by the time construction is complete. All mitigation should be, in addition, initiated and completed at least within two years of a resource impact due to a Civil Works project. NWF also supports proposals in S. 646 and S. 1987 that would disallow benefits for increased private property and service values derived from draining wetlands. Corps projects that would destroy hundreds of thousands of wetland acres should not be authorized because the extent of environmental destruction could never be fully mitigated.

 


Last month, the GAO issued a report assessing the Corps= fish and wildlife mitigation guidance, U.S. Army Corps of Engineers: Scientific Panel=s Assessment of Fish and Wildlife Mitigation Guidance (GAO-02-574, May 15, 2002). The GAO found that in a majority of the projects authorized since WRDA 1986 that required a fish and wildlife mitigation plan and that received construction appropriations, the Corps completed less than 50 percent of the required mitigation before project construction started. According to the GAO, the Corps has completed at least 50 percent of the mitigation before project construction in just a few cases. This report documents that while it is feasible for the Corps to complete half of the mitigation before starting project construction, the Corps= mitigation work has been shoddy and inconsistent.

 

Additionally, NWF objects to the Corps= reliance upon preservation or enhancement of existing lands or wetlands as the sole mitigation for destruction of natural habitats.  When mitigation is limited to protecting or enhancing existing habitats, a net loss of habitat occurs. The Corps has further entrenched this concept in its Regulatory Guidance Letter [RGL 01-01] on wetlands compensatory mitigation, allowing unlimited use of preservation of existing wetlands, and even upland areas as mitigation for the loss of natural wetlands.  NWF calls on the Committee to substantially elevate mitigation requirements, evaluation and monitoring for Civil Works projects, using the recommendations of the National Academy of Sciences report on Compensating for Wetlands Losses Under the Clean Water Act (National Research Council, 2001) to ensure that no net loss of ecosystem functions or values occur in the construction of Civil Works projects, as required by the 1990 WRDA Ano net loss of wetlands@ policy.

 

Corps= Construction Backlog Is Out of Control.

 

Mr. Chairman, the Corps has a huge construction backlog with some estimates as high as $52 billion dollars worth of projects. This enormous stockpile of uncompleted projects serves no one well. With hundreds of projects in various stages of construction and hundreds more having passed through the authorization process, the backlog can only be expected to increase. It prevents the Corps from completing a smaller number of projects sooner, which in turns adds to the ultimate cost of all projects. Congress authorizes new projects faster than the Corps can reasonably complete them. Unfortunately, this means that many new projects that would address contemporary needs, including critical environmental restoration projects, cannot be completed efficiently. The Corps continues to assume an optimal construction schedule in its cost-benefit analysis, even though the optimal schedule is not at all realistic because of the project backlog, which has the effect of artificially understating project costs and overstating project benefits.

 

Expedite Deauthorization for Outdated, Unconstructed Projects and Prioritize.

 

Throwing more money at the Corps= construction backlog without prioritizing and focusing the Corps= work only perpetuates the problem. In order to effectively address the ever-mounting project backlog, we urge the Committee to adopt a mechanism that identifies the projects that no longer make economic or environmental sense in light of current circumstances, and to impose some discipline on the new projects that are authorized. NWF urges the Committee to include provisions from S. 1987 that would expedite the current deauthorization process.

 


In addition, Congress could insure that high priority projects are completed in a timely manner by deauthorizing those projects that are no longer economically beneficial or that are proven to be environmentally destructive. Wasteful Corps projects can be replaced with positive developments by submitting them to rigorous economic analyses and environmental impact reviews. S. 1987 proposes updating the current 1.0 to 1.0 benefit-to-cost ratio, which was originally established in the 1930s, with a more modern 1.5 to 1.0 ratio. We urge the Committee to include such a provision in a WRDA to help prioritize among the nation=s water resource investments. Finally, NWF strongly supports President Bush=s policy decision in the fiscal year 2003 budget to focus the Corps on its traditional mission areas of flood damage reduction, navigation and environmental protection. 

 

Beach Sand Pumping Projects Are Exploding.

 

Funding for beach sand pumping projects is consuming increasingly larger portions of the Corps= budget. Currently, the federal government pays 65 percent of the cost of construction and periodic renourishment of beach projects authorized before 2000. Beginning in 2003, the federal portion will be 65 percent for construction and 50 percent for renourishment of new beach projects authorized after 2000. For currently authorized beach projects, it could easily cost federal taxpayers more than $10 billion in the next several decades to continue to put sand on beaches that is literally washed away to sea. In many cases, these projects tend to promote high-risk development along coastlines. The Corps is currently pumping sand onto the beaches of 18 of America=s 200 richest towns listed in Worth Magazine, including Gulf Stream, Florida, where the typical home sells for $1.5 million.

 

While sand pumping activities have existed in certain locations for decades, America=s coastlines have never been subject to the magnitude of sand pumping activity that would be represented if Congress stays on the present course of authorizing large numbers of new projects in each WRDA bill. For instance, virtually the entire Atlantic shoreline in New Jersey and half of North Carolina=s shoreline is authorized for beach sand pumping. NWF is extremely concerned about the long-term ecological effects that are likely to accompany such massive and expensive shoreline dredging and pumping activities. Sand pumping projects, which generally involve dredging sand from one location and dumping it on another, put aquatic wildlife and their habitat at great risk. Among the most immediate effects of beach projects is the burial of habitats and organisms living in these zones. Sand pumping projects also pose a problem to the nesting patterns of both sea turtles and bird species. Nesting turtles and birds can be easily deterred by the pipelines, lights and noise that accompany beach projects. In addition, the success of hatching eggs is affected by changes in the incubating environment, such as density, color, moisture content, compaction, and gas exchange of the beach sands. The dredged material used for the beaches often contains a different composite than the natural sands.

 

If sea levels rise as predicted B the predictions range from two feet per century for the next few hundred years to as much as fifteen feet by the year 2200[1] B erosion pressures will accelerate and the current response is unsustainable. We urge oversight and a much more thoughtful, scientifically-based response than we have seen to date to help guide a rational approach to erosion.

 

Reduce the Federal Government=s Burden for Sand Pumping Projects.

 


While there are instances where sand pumping may be either economically justified or can serve as temporary measures to allow communities that face erosion problems to make permanent adjustments, such as relocating at-risk buildings, a fundamental concern is that many believe this should not be largely a federal responsibility, given the range of demands on the federal budget. NWF strongly urges the Committee to seriously consider supporting a substantial reduction in the federal cost-share for beach nourishment activities, such as proposed by S. 1987 and the President=s fiscal year 2002 budget recommendation. In addition, we urge the Committee to resist attempts to allow more of these types of projects that are primarily for recreation rather than storm damage prevention. Until a much clearer picture can be gained of the ecological impacts that may be represented by expanding federal beach nourishment activities, the Committee should resist new authorizations.

 

A Race To The Bottom Among Ports and Harbors Is Bad for Taxpayers and the Environment.

 

Our nation=s ports and harbors are critically valuable resources for our economy and our environment and they must be managed in a manner that continues to support both. NWF has previously expressed our severe concern to the Committee that a number of ports and harbors are engaged in a race to deepen their channels in order to accommodate many of the largest and deepest draft ships operating on the trans-oceanic routes. At the same time, port authorities have sought to increase federal subsidies for deep draft harbor dredging by modifying current cost-share formulas to treat ports from 45 to 55 feet in depth the same as 45-foot depth or less general cargo ports. This would amount to a 25 percent increase in federal costs for deep draft dredging. The Corps is not currently dredging any commercial U.S. port deeper than 55 feet.

 

We also caution the Committee about relying on generalized future growth in trade predictions as a rationale for an across the board effort to deepen our ports. For instance, just two years ago at the time predictions were made that trade would double over the next 20 years, eastbound trans-Pacific trade grew at very high rates of 12% to 14% per year. Since then, trade traffic has seen far less significant growth. According to recent reports in the Journal of Commerce, cargo volumes in the eastbound Pacific increased by only 2% last year, and despite the nation=s recovering economy, volumes are expected to grow by single digit rates through next year. See, e.g., Bill Mongelluzzo, The Dire TransPacific, Journal of Commerce, March 18, 2002. The uncertainties associated with port and harbor needs argue even more strongly for the development of regional port planning to integrate the Corps program with national transportation policy.

 

The Corps Should Strive to Focus Deep Draft Port Dredging Activities to the Most Efficient, Environmentally Sound Ports.

 

We must invest in our ports wisely. Growth tends to be concentrated in a few major U.S. ports. More than half is concentrated in 20 ports and more than a quarter is handled by just five ports. In 1997, 25 ports handled 98 percent of the foreign container cargo, and the leading 10 ports accounted for 80 percent with the Los-Angeles-Long Beach port complex responsible for one-third of all container traffic. The 50 leading U.S. ports handle nearly 90 percent of all waterborne commerce. (NAS, Applying Information Systems to Ports and Waterways Management, 1999).

 


NWF supports provisions from S. 1987 that would require the Corps to conduct comprehensive coordinated planning to look regionally at shipping needs and the economic and environmental cumulative impacts of deepening ports and harbors. In WRDA 1986, Congress wisely established a cost sharing formula requiring that the very deepest ports B those with channels dredged deeper than 45 feet B pay a higher share of the costs for dredging than those below 45 feet. We believe any decision to increase the federal subsidy, such as the proposal sought by the port authorities to increase the subsidy by 25 percent, would unnecessarily fuel major expansions of capacity at too many locations that would have dire long-term environmental consequences. There is no reason to believe that the current formula will not allow the necessary capacity to meet the nation=s transportation needs where the business exists. We strongly oppose this cost-sharing change because it will undoubtedly fuel the race to the bottom, thereby unnecessarily wasting taxpayer resources and threatening further harm to the nation=s bays, rivers and estuaries. Instead, we urge the Committee to require regional port planning as an element of helping to guide the federal interest in ensuring U.S. ports can meet national transportation needs, consistent with protecting the environment.

 

21ST CENTURY VISION FOR THE CORPS: THE PREMIER ECOSYSTEM RESTORATION AND PROTECTION AGENCY.

 

The National Wildlife Federation is greatly encouraged by the substantial efforts made by the Committee and Congress in past WRDAs to authorize environmental programs, such as Section 1135 Project Modifications for Improvement of the Environment, Section 206 Aquatic Ecosystem Restoration, Floodplain Management Services, the Comprehensive Everglades Restoration Plan, the Upper Mississippi River Environmental Management Program, and numerous others. We remain concerned, however, that without a focused and highly disciplined Corps program, there will be, in fact, insufficient resources available for the Corps= environmental programs to make the critical contributions that the public seeks. We support adjustments to Corps flood damage reduction cost-sharing requirements that would increase the level of responsibility taken by local and state governments in managing flood risk. Among the ideas that have significant merit is to establish a sliding cost-share formula that gives communities incentives to reduce and manage their flood risk.

 

We are also especially concerned, for instance, that the Corps has received no funding to date for the landmark Challenge 21 program, which provides the Corps with substantial opportunities to add nonstructural approaches to its flood damage reduction programs. These are areas where the need for priority-setting becomes of paramount importance.

 

CONCLUSION.

 


In sum, the Corps of Engineers has a vital role to play in managing the nation=s water resources. Continuing business as usual, however, is not acceptable. Several new reports by the National Academy of Sciences and others, the results of extensive audits and investigations, as well as much thoughtful legislation, have provided critically important recommendations for long-needed reforms. We applaud the Corps of Engineers for taking a first step in signaling its commitment to a sustainable environment by formalizing a set of AEnvironmental Operating Principles@ applicable to its decision-making and programs. These principles were recently articulated by the Chief of Engineers, Lt. General Flowers, at the dedication of the Davis Pond Fresh Water Diversion Project in Louisiana. We urge the Environment and Public Works Committee to directly address the Corps= crisis in confidence by including important legislative reforms in the next WRDA. These reforms would provide critical direction for all Corps programs, including direction for what may be among the Corps= most important functions in the twenty-first century B ecosystem restoration and protection.

 

Chairman Jeffords and Ranking Member Smith, once again, thank you for the opportunity to present our views. We look forward to working with you and the other members of the Committee to help bring the Corps into the 21st Century by incorporating critically needed reforms in the next WRDA legislation. I am happy to respond to any questions the Committee Members may have.


APPENDIX

 

The State of the Nation=s Aquatic Resources

 

The U.S. leads the world in species number for many freshwater organisms including insects, snails, salamanders, turtles, and mussels. It also ranks high for subterranean invertebrates and freshwater fishes.  This vast array of diversity is primarily the result of the unparalleled system of watersheds that filter through the country.  It is no coincidence that the greatest species loss has occurred in the precise regions where large water projects have rearranged the natural landscape.  The impacts of water development affect 30 percent of the listed endangered species, ranking behind only agriculture and commercial development. According to the Association for Biodiversity Information, ASpecies that depend on freshwater ecosystems are, as a whole, faring the worst of any group of U.S. organisms.@ The deteriorating conditions are undeniable with the list of extinct/imperiled species growing every year.  Modern science has concluded that the three leading threats to aquatic species are agricultural non-point pollution, alien species, and altered hydraulic regimes due to dams and impoundments.  Many Corps projects and programs are directly involved in exacerbating these threats.

 

 

 

Global Significance of Select U.S. Plant and Animal Groups/Species:

 

Mammal:                     416 in U.S. out of 4600 globally                     9% of total

Bird:                            768 in U.S. out of 9700 globally                     8% of total

Reptile:                       283 in U.S. out of 6600 globally                     4% of total

Freshwater Fish:         799 in U.S. out of 8400 globally                     10% of total

Amphibian:                 231 in U.S. out of 4400 globally                     5%  of total

Salamander:                140 in U.S. out of 350 globally                       40% of total

Freshwater Mussel:     292 in U.S. out of 1,000 globally                    29% of total

Freshwater Snails:      661 in U.S. out of 4,000 globally                    7% of total

Crayfishes:                  322 in U.S. out of 525 globally                       61% of total

 

Freshwater insects:

Caddisfly:                   1400 in U.S. out of 10769 globally                 13% of total

Mayfly:                        590 in U.S. out of 1967 globally                     30% of total

Stonefly:                      610 in U.S. out of 1525 globally                     40% of total

 

 

 

 

 

 

All information in this Appendix is from Precious Heritage:  The Status of Biodiversity in the United States.  The Nature Conservancy & Association for Biodiversity Information.  Oxford University Press (2000).



Disappearance of U.S. Aquatic Species

Sources of Harm For at Risk Species

 

Percentage of federal endangered, threatened, and proposed species harmed by types of habitat destruction and degradation.

 


 

 

 

 

 

Overall

(n=1207)

 

 

Vertebrates

(n=329)

 

 

Inverte-brate

(n=155)

 

 

Bird

(n=91)

 

 

Reptile

(n=39)

 

 

Amphibian

(n=16)

 

 

Fish

(n=116)

 

 

Insect

(n=39)

 

 

Mussel

(n=69)

 

Mollusk

(n=23)

 

Agriculture

 

38

 

40

 

57

 

42

 

33

 

63

 

45

 

56

 

64

 

35

 

Commercial

Development

 

35

 

30

 

42

 

33

 

56

 

44

 

16

 

67

 

29

 

13

 

Water Development

 

30

 

47

 

66

 

22

 

28

 

63

 

91

 

21

 

99

 

48

 

Outdoor Recreation

 

27

 

16

 

19

 

15

 

31

 

25

 

9

 

41

 

4

 

26

 

Livestock grazing

 

22

 

17

 

10

 

20

 

8

 

19

 

16

 

15

 

1

 

9

 

Pollutants

 

20

 

27

 

66

 

10

 

21

 

25

 

55

 

26

 

97

 

48

 

Infrastructure development

 

17

 

16

 

12

 

8

 

28

 

38

 

17

 

23

 

6

 

9

 

 

                                                                        June 12, 2002

 


VIA FACSIMILE

 

The Honorable James Connaughton, Chair

Council on Environmental Quality

722 Jackson Place, NW

Washington, DC 20503

 

The Honorable Mitchell E. Daniels, Jr., Director

Office of Management and Budget

725 Seventeenth Street, NW

Washington, DC 20503

 

                       SUBJECT:      U.S. Army Corps of Engineers

Dear Messrs. Connaughton and Daniels:

 

We are writing to urge the Administration to work with members of Congress and with our conservation, taxpayer, and professional organizations to support legislation that will reform the way the Corps of Engineers (Corps) plans, evaluates, and implements water resources projects. The Corps’ failure to address the contemporary needs of communities in an environmentally sound and cost-efficient manner is taking a tremendous toll on the nation’s natural and financial resources. Your leadership in this effort is critical.

 

The Corps’ implementation of its much touted nationwide project “pause” starkly underscores the need for the Bush Administration and Congress to act now to reform the Corps. We had hoped that the project “pause” was a genuine sign of the Corps’ interest in ensuring that its water resource projects were economically and environmentally sound. Unfortunately, the review appears to have been little more than a charade, and the Corps has made it abundantly clear that it is either unwilling or unable to reform itself.

 

First, less than three weeks after announcing the “pause,” the Corps announced that it had reviewed 172 projects and cleared 118 to move forward. Only eight projects were flagged for additional review as a result of this process (with the remainder already undergoing reevaluation due to previously identified problems). That timeline made it abundantly clear that General Griffin’s direction to conduct a new economic analysis for projects approved prior to FY 99 was not followed.

 

Second, just a few days later, the Corps released a “corrected” list that deviated in significant ways from the first list. The second list identifies only 164 projects as having been reviewed, clearing 80 to proceed (with the remainder already undergoing reevaluation due to previously identified problems). Again, only eight projects were said to require additional review as a result of the project pause directive.

 

With no explanation, the Corps completely removed from the second list some of the worst projects that were identified on the original list with the nomenclature “review complete.” These projects include the Grand Prairie Irrigation Demonstration Project in Arkansas, the Yazoo Pumps Project in Mississippi, St. John’s Bayou Project in Missouri and the Inner Harbor Navigation Canal (Industrial Canal) Project in Louisiana. In addition to being costly, these projects are highly controversial and would destroy some of America’s most valuable wetlands and aquatic habitat. Because the Corps has left the public completely in the dark on the process used in its review, the only conclusion we can reach is that although the Corps originally announced to Congress and the public that these projects had in fact been reviewed, the reviews never occurred. If the Corps’ review and reevaluation process is to have any credibility, these projects must be fully and openly re-evaluated.

 

Third, in addition to the Corps’ apparent inability to be able to accurately identify projects that were reviewed, the list contains glaring omissions of projects that most certainly should have been reevaluated. For example, the list does not include the Dallas Floodway Extension project in Texas – an authorized project for which construction has not begun. Not only did the Office of Management and Budget inform the Corps that they had failed to comply with their own planning guidance for this project, but a U.S. District Court also ordered the Corps to reevaluate the project’s cumulative environmental impacts.

 

Finally, the project reevaluation was conducted behind closed doors with no involvement from the public, other federal and state agencies, or apparently the Administration. The Corps has not identified or described the information reviewed, the results of each review, or the documentation supporting its conclusions. The fact that the Corps originally cleared more than 100 projects in less than three weeks – including some of the most highly questionable and controversial Corps projects – and then substantially revised the list of projects reviewed and their status (once again all behind closed doors), gives the public no confidence that the “cleared” projects represent a sound and environmentally sustainable investment.

 

Instead, the Corps’ actions have increased the public’s lack of confidence in the Corps’ ability to plan water resource projects in an objective and reliable manner. Now more than ever, Congress must enact meaningful Corps reforms to improve the broken process and help restore faith in this scandal-plagued agency. The Corps reform bills introduced in the Senate and House (S. 1987,

S. 646, H.R. 1310 and H.R. 2353) contain crucial reforms that cannot be postponed. We urge the Administration to actively support these legislative proposals as Congress considers authorizing even more water resource projects during debate over the Water Resource Development Act.

 

We very much appreciate the leadership of the Bush Administration in proposing a more environmentally responsible budget for the Corps of Engineers for FY 03, and hope that you will fight to keep this year’s budget from growing as it moves through Congress. We also hope that the Administration will work to make the Corps’ entire program more environmentally and fiscally responsible by actively supporting the important legislative proposals directed at reforming the Corps of Engineers.

 

                                                                                          Sincerely,

 


Bradford T. McLane

Executive Director

Alabama Rivers Alliance

 

Kathy Andria

President

American Bottom Conservancy

 

S. Elizabeth Birnbaum

Director of Government Affairs

American Rivers

 

David McLain

Executive Director

Apalachicola Bay and Riverkeeper

 

David Gowdey

Executive Director

Arizona Wildlife Federation

 

Daniel DeVun

Vice President

Arkansas Nature Alliance

 

Jim Wood

Representative

Arkansas Wildlife Federation

 

Rob Fisher

Conservation Director

Audubon Arkansas

 

Sidney Maddock

Environmental Analyst

Biodiversity Legal Foundation

 

John Koeferl

Founding Board Member

Citizens Against Widening the Industrial Canal

 

Jamie Matera

Outreach Coordinator

Coast Alliance

Peter Huhtala

Executive Director

Columbia Deepening Opposition Group

 

Matthew Van Ess

Director

Columbia River Estuary Study Taskforce

 

Patricia A. Pendergrast

President

Connecticut Ornithological Association

 

Karen Blue

Executive Director

Conservation Council for Hawaii

 

Michael E. Riska

Executive Director

Delaware Nature Society

 

Maya K. van Rossum

Delaware Riverkeeper

Delaware Riverkeeper Network

 

Val Washington

Executive Director

Environmental Advocates of New York

 

Mona Shoup

Chair

Friends of Clear Creek

 

Erich Pica

Director, Green Scissors Campaign

Friends of the Earth

 

Manley K. Fuller, III

President

Florida Wildlife Federation

 

Jim Blackburn

Chair, Galveston Bay Conservation and Preservation Association

Jerry L. McCollum

President and CEO

Georgia Wildlife Federation

 

Margaret Wooster

Executive Director

Great Lakes United

 

Cyn Sarthou

Executive Director

Gulf Restoration Network

 

Marilyn Blackwell

President

Help Save The Apalachicola River Group

 

Pamela Dashiell

President

Holy Cross Neighborhood Association

 

Steven G. Sorensen

Past President

Kansas Wildlife Federation

 

Tom Fitzgerald

Director

Kentucky Resources Council, Inc.

 

Judy Petersen

Executive Director

Kentucky Waterways Alliance, Inc.

 

Cam Davis

Executive Director

Lake Michigan Federation

 

Larry Mitchell

President

League of Ohio Sportsmen

 

Mark F. Ten Eyck

Advocacy Director

Minnesota Center for Environmental Advocacy

 

Kenneth Hiemenz

President

Minnesota Conservation Federation

 

Tim Sullivan

Executive Director

Mississippi River Basin Alliance

 

Bea Covington

Executive Director

Missouri Coalition for the Environment

 

Perry Plumart

Director of Government Relations

National Audubon Society

 

Jamie Rappaport Clark

Senior Vice President

National Wildlife Federation

 

Marian Maas, Ph.D.

Conservation Programs Chair

Nebraska Wildlife Federation

 

Jim Stephenson

Program Analyst

North Carolina Coastal Federation

 

Chuck Rice

Executive Director

North Carolina Wildlife Federation

 

Nina Bell, J.D.

Executive Director

Northwest Environmental Advocates

 

Vicki Deisner

Executive Director

Ohio Environmental Council

 

Ella F. Filippone

Executive Administrator

Passaic River Coalition

 

 

Jim Stevens

President

People to Save the Sheyenne

 

Gerald H. Meral, Ph.D.

Executive Director

Planning and Conservation League

 

Clark Bullard

Member of the Board

Prairie Rivers Network

 

Magi Shapiro

Member of the Board

Public Employees for Environmental Responsibility

 

Todd Ambs

Executive Director

River Alliance of Wisconsin

 

Mike Fremont

President

Rivers Unlimited

 

Angela Viney

Executive Director

South Carolina Wildlife Federation

 

Chris Hesla

Executive Director

South Dakota Wildlife Federation

 

Gwen Griffith, DVM, MS

Program Director

Tennessee Environmental Council

 

Michael Utt

President

The Ohio Smallmouth Alliance

 

Melanie Winter

Director

The River Project

 

 

Wilfred Cwikiel

Water Resource Program Director

Tip of the Mitt Watershed Council

 

Kelly D. Lowry, Esq.

General Counsel and Water Program Director

Vermont Natural Resources Council

 

Larry Baesler

Executive Director

Wyoming Wildlife Federation

 

 



[1] See WORKING GROUP 1,INTERGOVERNMENTAL PANEL ON CLIMATE CHANGE,CLIMATE CHANGE 1995:THE SCIENCE OF CLIMATE CHANGE, at 6 (estimating that IPCC =s best estimate is that global sea level will rise 49 cm from 1990-2100).  See also JAMES G.TITUS &VIJAY K. NARAYANAN, U.S. ENVIRONMENTAL PROTECTION AGENCY, THE PROBABILITY OF SEA LEVEL RISE iii, 145-46 (1995)(explaining that along much of the U.S. coast sea level is likely to rise about 10 cm more than the global average).